A Change Order. is a written instrument issued after execution of the Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following: 9.1.1.1 The scope of the change in the Work; 9.1.1.2 The amount of the adjustment to the Contract Price; and 9.1.1.3 The extent of the adjustment to the Contract Time(s).
Appears in 4 contracts
Sources: Progressive Design Build Agreement, Design Build Contract, Design Build Contract
A Change Order. is a written instrument amendment to the Contract Documents signed by the Owner, the Architect and the Contractor, issued after the execution of the Agreement signed by Owner and Design-BuilderContract, stating their agreement upon all of the following:
9.1.1.1 The scope of the authorizing a change in the Work;
9.1.1.2 The amount of the Work or an adjustment to in the Contract Price; and
9.1.1.3 The extent of the adjustment to Amount or the Contract Time(s)Time. The Contract Amount and the Contract Time may be changed only by Change Order.
Appears in 3 contracts
Sources: Construction Manager at Risk Services Agreement, Construction Manager at Risk (Cmar) Services Agreement, Guaranteed Maximum Price Agreement
A Change Order. is a written instrument issued after execution of the Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following:
9.1.1.1 .1 The scope of the change in the Work;
9.1.1.2 .2 The amount of the adjustment to the Contract Price; and
9.1.1.3 .3 The extent of the adjustment to the Contract Time(s).
Appears in 2 contracts
Sources: Progressive Design Build Agreement, Progressive Design Build Agreement
A Change Order. is a written instrument issued after execution of the Agreement signed by Owner Design-Builder and Design-BuilderBuild Subcontractor, stating their agreement upon all of the following:
9.1.1.1 12.3.1.1 The scope of the change in the Work;
9.1.1.2 12.3.1.2 The amount of the adjustment to the Contract Price; and
9.1.1.3 12.3.1.3 The extent of the adjustment to the Contract Time(s)times for completion of the Work.
Appears in 2 contracts
Sources: Standard Form of Agreement Between Design Builder and Design Build Subcontractor, Standard Form of Agreement Between Design Builder and Design Build Subcontractor Lump Sum
A Change Order. is a written instrument issued after execution of prepared by the Agreement signed Contracting Authority and executed by Owner the Contracting Authority and Design-Builder, DB stating their agreement upon all of the following:
9.1.1.1 The scope of the 7.2.1.1 a change in the Work;
9.1.1.2 The 7.2.1.2 the amount of the adjustment to of the Contract PriceSum, if any; and
9.1.1.3 The 7.2.1.3 the extent of the adjustment to of the Contract Time(s)Times, if any.
Appears in 2 contracts
Sources: Professional Services, Professional Services
A Change Order. is a written instrument issued after execution of the this Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following:
9.1.1.1 a) The scope of the change in the Work;
9.1.1.2 b) The amount of the adjustment to the Contract Price; and
9.1.1.3 c) The extent of the adjustment to the Contract Time(s).
Appears in 2 contracts
Sources: Lump Sum Design Build Agreement (Red Trail Energy, LLC), Lump Sum Design Build Agreement (Red Trail Energy, LLC)
A Change Order. is a written instrument issued after execution of the Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following:
9.1.1.1 The scope of the change in the Work;
9.1.1.2 The amount of the adjustment to the Contract Price, if any; and
9.1.1.3 The extent of the adjustment to the Contract Time(s), if any.
Appears in 1 contract
A Change Order. is a written instrument issued after execution of the this Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following:
9.1.1.1 The (a) the scope of the change in the Work;
9.1.1.2 The (b) the amount of the adjustment to the Contract Price; and
9.1.1.3 The (c) the extent of the adjustment to the Contract Time(scontract time(s).
Appears in 1 contract
Sources: Lump Sum Design Build Agreement (Siouxland Ethanol, LLC)
A Change Order. (“Change Order”) is a written instrument issued after execution of the this Agreement signed by Owner and Design-BuilderVendor, equitably adjusting the Contract Price, Work Schedule or other affected terms and conditions of the Agreement, stating their agreement upon any or all of the following:
9.1.1.1 (a) The scope of the change in the Scope of Work;
9.1.1.2 (b) The amount of the adjustment to the Contract Price; and, if any;
9.1.1.3 (c) The extent of the adjustment to the Contract Time(s)Work Schedule, if any; and
(d) The equitable adjustment of other affected terms and conditions of this Agreement as a consequence of the Change Order.
Appears in 1 contract
Sources: Solar Field Agreement
A Change Order. is a written instrument issued after execution of the Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following:
9.1.1.1 1. The scope of the change in the Work;
9.1.1.2 2. The amount of the adjustment to the Contract Price; and
9.1.1.3 3. The extent of the adjustment to the Contract Time(s).
Appears in 1 contract
Sources: Design Build Agreement
A Change Order. is a written instrument issued after execution of the Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following:
9.1.1.1 .1 The scope of the change in the Work;
9.1.1.2 .2 The amount of the adjustment to the Contract Price; and
9.1.1.3 .3 The extent of the adjustment to the Contract Time(s).
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Design Builder Lump Sum (Husker Ag Processing LLC)
A Change Order. is a written instrument issued after execution of prepared by the Agreement Engineer and signed by Owner the Owner, Contractor and Design-BuilderEngineer, stating their agreement upon all of the following:
9.1.1.1 The scope of the 7.2.1.1 a change in the Work;
9.1.1.2 The 7.2.1.2 the amount of the adjustment to in the Contract Price; Sum, if any, and
9.1.1.3 The 7.2.1.3 the extent of the adjustment to in the Contract Time(s)Time, if any.
Appears in 1 contract
Sources: Construction Agreement
A Change Order. is a written instrument issued after execution of prepared by the Agreement Architect and signed by Owner the Owner, Contractor and Design-BuilderArchitect, stating their agreement upon all of the following:
9.1.1.1 The scope of the .1 a change in the Work;
9.1.1.2 The ; .2 the amount of the adjustment to adjustment, if any, in the Contract PriceSum; and
9.1.1.3 The extent of the adjustment to the Contract Time(s).
Appears in 1 contract
Sources: General Conditions of the Contract for Construction
A Change Order. is a written instrument issued after execution of prepared by the Agreement Consultant and signed by the Owner and Design-Builderthe Contractor, stating their agreement upon all of the following:
9.1.1.1 The scope of .1 the change in the Work;
9.1.1.2 The ; .2 the amount of the adjustment to in the Contract PriceSum, if any; and
9.1.1.3 The and .3 the extent of the adjustment to in the Contract Time(s)Time, if any.
Appears in 1 contract
Sources: Agreement Between Owner and Contractor for Furniture, Furnishings and Equipment
A Change Order. is a written instrument issued after execution of the Agreement prepared by Architect and signed by Owner and Design-Builder, Construction Manager stating their agreement upon all of the following:
9.1.1.1 The scope of the .1 a change in the Work;
9.1.1.2 The ; .2 the amount of the adjustment to in the Contract PriceGMP, if any; and
9.1.1.3 The extent of the adjustment to the Contract Time(s).
Appears in 1 contract
Sources: Construction Management Agreement
A Change Order. is a written instrument issued after execution of prepared by the Agreement Architect and signed by Owner the Owner, Contractor and Design-BuilderArchitect, stating their agreement upon all of the following:
9.1.1.1 The scope of the .1 change in the Work;
9.1.1.2 The .2 the amount of the adjustment to adjustment, if any, in the Contract PriceSum; and
9.1.1.3 The .3 the extent of the adjustment to adjustment, if any, in the Contract Time(s)Time.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor (Corixa Corp)
A Change Order. is a written instrument issued after execution of prepared by the Agreement Architect and signed by Owner the Owner, the Contractor, the Architect and Design-Builderthe Owner's lender, stating their agreement upon all of the followingfollowing for the item covered in each Change Order as well as the cumulative effect and impact of all previous Change Orders:
9.1.1.1 The scope of the .1 a change in the Work;
9.1.1.2 The amount of the adjustment to the Contract Price; and
9.1.1.3 The extent of the adjustment to the Contract Time(s).
Appears in 1 contract
Sources: Construction Contract (National Instruments Corp /De/)
A Change Order. is a written instrument issued after execution of the Agreement signed by Owner and Design-Builder, stating their agreement upon all of the following:by
9.1.1.1 12.3.1.1 The scope of the change in the Work;
9.1.1.2 12.3.1.2 The amount of the adjustment to the Contract Price; and
9.1.1.3 12.3.1.3 The extent of the adjustment to the Contract Time(s)times for completion of the Work.
Appears in 1 contract
Sources: Design Build Subcontract Agreement
A Change Order. is a written instrument issued after execution of prepared by the Agreement Engineer and signed by Owner the Owner, Contractor and Design-BuilderEngineer, stating their agreement upon all of the following:
9.1.1.1 The scope of the : .1 a change in the Work;
9.1.1.2 The ; .2 the amount of the adjustment to in the Contract Price; and
9.1.1.3 The Sum, if any, and .3 the extent of the adjustment to in the Contract Time(s)Time, if any.
Appears in 1 contract
Sources: Construction Contract
A Change Order. is a written instrument issued after execution of the Agreement signed by Owner and Design-Design- Builder, stating their agreement upon all of the following:
9.1.1.1 .1 The scope of the change in the Work;
9.1.1.2 .2 The amount of the adjustment to the Contract Price; and
9.1.1.3 .3 The extent of the adjustment to the Contract Time(s).
Appears in 1 contract
Sources: Design Build Agreement
A Change Order. is a written instrument issued after execution of prepared by the Agreement Architect and signed by Owner the Owner, Contractor and Design-BuilderArchitect, stating their agreement upon all of the following:
9.1.1.1 The scope of the 1 a change in the Work;
9.1.1.2 The ; .2 the amount of the adjustment to in the Contract PriceSum, if any; and
9.1.1.3 The and .3 the extent of the adjustment to in the Contract Time(s)Time, if any.
Appears in 1 contract
Sources: Architectural Services Agreement