Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power projects.

Appears in 25 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar Solar power projects.

Appears in 20 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power Solar Power projects.

Appears in 16 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government UPPCL to carry out testing and certification for the solar Solar power projects.

Appears in 3 contracts

Sources: Power Purchase Agreement (Ppa), Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall may be required to get the Project certified for the requisite acceptance/acceptance / performance test as may be laid down by Central Electricity Authority or an agency identified by the central government agency, in consultation with PSPCL to carry out testing and certification for the solar power projects.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government government/State Government/LED to carry out testing and certification for the solar power projectsSolar Power project.

Appears in 2 contracts

Sources: Power Purchase Agreement (Ppa), Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government/state government to carry out testing and certification for the solar power projectsSolar Power project.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/acceptance / performance test as may be laid down by Central Electricity Authority or an agency identified by the central or state government to carry out testing and certification for the solar power projectsSolar powerprojects.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/acceptance/ performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar Solar power projects.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power projects.central

Appears in 1 contract

Sources: Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central central/state government to carry out testing and certification for the solar power projects.

Appears in 1 contract

Sources: Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 14.6.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power projects.

Appears in 1 contract

Sources: Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 4.7.1. Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power Solar Power projects.

Appears in 1 contract

Sources: Power Purchase Agreement

Acceptance/Performance Test. 4.7.1 4.8.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power Solar Power projects.

Appears in 1 contract

Sources: Power Purchase Agreement