Access Following Construction. After the occurrence of the Actual Completion Date [a Phase Actual Completion Date] the Authority shall grant to Project Co and Project Co Parties, or procure that Project Co and Project Co Parties are granted, access to the Facilities subject only to the Reserved Rights, the Title Conditions and the provisions of this Agreement and solely for the purposes of: carrying out the Project Operations (other than those Project Operations for which Project Co is granted rights pursuant to Clause 9.1 (Access During Construction)); remedying Defects and carrying out Snagging Matters [relating to that Phase]; and exercising the Ancillary Rights. Such rights shall terminate on the Expiry Date or (if earlier) the Termination Date.
Appears in 2 contracts
Sources: Project Agreement, Project Agreement