Additional or Substitute Bonds. A. If at any time the Owner, for justifiable cause, shall be or become dissatisfied with any Surety or Sureties than upon the performance or payment bonds, the Contractor shall, within five (5) calendar days after notice from the Owner so to do, substitute an acceptable bond (or bonds) in such form and sum and signed by such other Surety or Sureties as may be acceptable to the Owner. The Contractor shall pay the premiums on such bonds with no additional expense to the Owner. No further payments shall be deemed due nor will be made until the new Surety or Sureties shall have furnished such as acceptable bond to the Owner.