Additional Tests and Inspections. 6.20.1 If before or after Substantial Completion the A/E or Contracting Authority determines that any portion of the Work requires special inspection, testing, or approval not otherwise required under the Contract Documents, the A/E shall order such inspection, testing, or approval. 6.20.1.1 If the special inspection, testing, or approval reveals Defective Work, the CM shall pay all associated costs and will not be entitled to any related adjustment of the Contract Times. Those costs may include, but are not limited to: .1 the cost of the special inspection, testing, or approval; .2 the cost of conducting the special inspection, testing, or approval on similar Work regardless of whether the similar Work is also revealed as Defective Work; .3 the cost of additional special inspections, testing, or approvals to evaluate remedial Work; .4 the cost of correcting the Defective Work; and