Adjustment of Contract Sum. 8.4.1 For the purpose of any adjustment of the Contract Sum for a Variation: 8.4.1.1 if practicable, the value of a Variation must be agreed by the Contractor and the Council before the Contractor commences to execute the Variation;
Appears in 1 contract
Sources: Minor Works Agreement
Adjustment of Contract Sum. 8.4.1 For the purpose of any adjustment of the Contract Sum for a Variation: 8.4.1.1 if practicable, the value of a Variation must be agreed by the Contractor and the Council before the Contractor commences to execute the Variation;; if the value of a Variation is not agreed by the Contractor and the Council, the value must be determined by the Council in accordance with the rates and the criteria set out in Item 12 of the Schedule; a Variation must be valued as soon as practicable, and the Contractor must promptly and diligently supply to the Council all information relevant to the valuation. Time
Appears in 1 contract
Sources: Minor Works Agreement
Adjustment of Contract Sum. 8.4.1 For the purpose of any adjustment of the Contract Sum for a Variation: 8.4.1.1 13.
4.1 if practicable, the value of a Variation must be agreed by the Contractor Supplier and the Council before the Contractor Supplier commences to execute the Variation;
Appears in 1 contract
Sources: Construction Contract
Adjustment of Contract Sum. 8.4.1 β For the purpose of any adjustment of the Contract Sum for a Variation: 8.4.1.1 :
8.4.1 if practicable, the value of a Variation must be agreed by the Contractor and the Council before the Contractor commences to execute the Variation;
8.4.2 if the value of a Variation is not agreed by the Contractor and the Council, the value must be determined by the Council in accordance with the rates and the criteria set out in Item 12 of the Schedule;
Appears in 1 contract
Sources: Minor Works Agreement