Common use of After termination under Sub Clause in Contracts

After termination under Sub. 13.3.1, the Contractor shall: a. cease all further work, except for such work as may be necessary and instructed by the Engineer for the purpose of making safe or protecting those parts of the Works already executed, and any Work required to leave the Site in a clean and safe condition, b. hand over all Construction and/or Manufacture Documents, Plant, Rolling stock, and Materials for which the Contractor has received payment, c. hand over those parts of other Works executed by the Contractor up to the date of termination, and d. remove all Contractor's Equipment which is on the Site and repatriate all his staff and labour from the Site. Any such termination shall be without prejudice to any other right of the Contractor under the Contract.

Appears in 3 contracts

Sources: General Conditions of Contract, General Conditions of Contract, General Conditions of Contract