Amending and Supplementing the Contract. A. The Contract may be amended or supplemented by a Change Order, a Work Change Directive, or a Field Order. B. If an amendment or supplement to the Contract includes a change in the Contract Price or the Contract Times, such amendment or supplement must be set forth in a Change Order. C. All changes to the Contract that involve (1) the performance or acceptability of the Work,
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Amending and Supplementing the Contract. A. The Contract may be amended or supplemented by a Change Order, a Work Change Directive, or a Field Order.
B. If an amendment or supplement to the Contract includes a change in the Contract Price or the Contract Times, such amendment or supplement must be set forth in a Change Order.
C. All changes to the Contract that involve (1) the performance or acceptability of the Work,
Appears in 1 contract
Sources: Construction Contract
Amending and Supplementing the Contract. β
A. The Contract may be amended or supplemented by a Change Order, a Work Change Directive, or a Field Order.
B. If an amendment or supplement to the Contract includes a change in the Contract Price or the Contract Times, such amendment or supplement must be set forth in a Change Order.
C. All changes to the Contract that involve (1) the performance or acceptability of the Work,
Appears in 1 contract
Sources: Construction Contract