Amount of Pre. COD Security. On or before the date specified in Section 3.1.9(a)(i), Seller shall post and maintain Performance Assurance in favor of PGE, equal in each case to $200 per kW of Nameplate Capacity (the “Pre-COD Security”).
Appears in 1 contract
Amount of Pre. COD Security. On or before the date specified in Section 3.1.9(a)(i3.1.9(a)(ii), Seller shall post and maintain Performance Assurance in favor of PGE, equal in each case to $200 per kW of Nameplate Capacity (the “Pre-COD Security”).
Appears in 1 contract