An Excusable. Delay is Compensable when: 1. The delay causes the work to extend beyond the Contract Time, and 2. The delay is caused by circumstances beyond the control of the Construction Manager or its subcontractors, materialmen, suppliers, or vendors, and 3. The delay is caused by an act or omission of the Owner, or of the Architect/Engineer, provided however, delays caused by permitting agencies, whether or not part of DCSB, are Non-Compensable Excusable Delays to the extent that such delays were not caused by the Construction Manager; permitting delays caused by the Construction Manager are non-excusable delays.
Appears in 7 contracts
Sources: Construction Management Agreement, Construction Management Services Agreement, Construction Management Agreement