AND DELIVERY OF DOCUMENTS. 2.1 On or prior to execution of this Agreement: 2.1.1 DBFM Co shall: (one) deliver to the Authority the documents referred to in Part A of Section 1 of Schedule Part 2 (Completion Documents); and (two) exhibit to the Authority fully executed versions of the documents referred to in Part B of Section 1 of Schedule Part 2 (Completion Documents) (unless the requirement to deliver or exhibit any such document is waived by the Authority by written notice to DBFM Co); and 2.1.2 the Authority shall deliver to DBFM Co the documents referred to in Section 2 (Documents to be delivered by the Authority) of Schedule Part 2 (Completion Documents) (unless the requirement to deliver any such document is waived by DBFM Co by written notice to the Authority). 2.2 DBFM Co undertakes to obtain and deliver to the Authority on or before the earliest to occur of: (i) 10 Business Days of the date of appointment of each Key Sub-Contractor by the Contractor; and (ii) 10 Business Days prior to the day on which the relevant Key Sub-Contractor commences any relevant sub-contract works on the Sites and/or commences any off-site fabrication related to the relevant sub-contract works, a collateral warranty agreement between the relevant Key Sub-Contractor and the Authority, which collateral warranty agreement shall be in the form of the Key Sub-Contractor Collateral Agreement (subject to any reasonable amendments proposed by the relevant Key Sub-Contractor and approved by the Authority acting reasonably) validly executed in self proving form by the Key Sub-Contractor, together with a certified copy of the signed sub- contract entered into between the Contractor and the Key Sub-Contractor. 2.3 The Authority shall deliver to DBFM Co a certified copy of the letter from the Scottish Government to the Authority confirming the final terms of the revenue grant funding to be provided to the Authority in respect of the Project following financial close within 5 Business Days of the Authority’s receipt of the same. 2.4 DBFM Co shall deliver to the Authority 2 copies of the Project Bible within 15 Business Days of Financial Close.
Appears in 1 contract
Sources: Construction Contract
AND DELIVERY OF DOCUMENTS. 2.1 On or prior to execution of this Agreement:
2.1.1 DBFM Co shall: (one) deliver to the Authority the documents referred to in Part A of Section 1 (Documents to be delivered by DBFM Co) of Schedule Part 2 (Completion Documents); and (two) exhibit to the Authority fully executed versions of the documents referred to in Part B of Section 1 (Documents to be delivered by DBFM Co) of Schedule Part 2 (Completion Documents) (unless the requirement to deliver or exhibit any such document is waived by the Authority by written notice to DBFM Co); and
2.1.2 the Authority shall deliver to DBFM Co the documents referred to in Section 2 (Documents to be delivered by the Authority) of Schedule Part 2 (Completion Documents) (unless the requirement to deliver any such document is waived by DBFM Co by written notice to the Authority).
2.2 DBFM Co undertakes to obtain and deliver to the Authority on or before the earliest to occur of: (i) 10 Business Days of the date of appointment of each Key Sub-Contractor by the Contractor; and (ii) 10 Business Days prior to the day on which the relevant Key Sub-Contractor commences any relevant sub-contract works on the Sites Site and/or commences any off-site fabrication related to the relevant sub-contract works, a collateral warranty agreement between the relevant Key Sub-Contractor and the Authority, which collateral warranty agreement shall be in the form of the Key Sub-Contractor Collateral Agreement (subject to any reasonable amendments proposed by the relevant Key Sub-Contractor and approved by the Authority acting reasonably) validly executed in self proving form by the Key Sub-Contractor, together with a certified copy of the signed sub- contract entered into between the Contractor and the Key Sub-Contractor.
2.3 The Authority shall deliver to DBFM Co a certified copy of the letter from the Scottish Government to the Authority confirming the final terms of the revenue grant funding to be provided to the Authority in respect of the Project following financial close within 5 Business Days of the Authority’s receipt of the same.
2.4 DBFM Co shall deliver to the Authority 2 copies of the Project Bible within 15 Business Days of Financial Close.