APPLICABLE TARIFF. 9.1 The SPD shall be entitled to receive the Tariff of Rs. / kWh [Insert the Tariff discovered through the bidding process conducted by SECI], fixed for the entire term of this Agreement, with effect from the SCD, for the power sold by the Buyer to the Buying Entity for the scheduled energy as reflected in the Energy Accounts. In case of early part-commissioning, till SCD, subject to the consent for such purchase by the Buying Utility, SECI may purchase the generation @ 75% (seventy-five per cent) of the PPA tariff. However, in case the entire Project capacity is commissioned prior to SCD, SECI may purchase energy supplied till SCD at [Insert Tariff]/kWh. In both the cases of early part or full commissioning of the Project, the Applicable Tariff for the commissioned Project shall be 9.2 Any excess generation over and above energy specified in Article 4.4.1, will be purchased by SECI at a tariff of 75% of the tariff as per Article 9.1, provided the Buying Entity consents for purchase of such excess generation. Any energy produced and flowing into the grid before SCD shall not be at the cost of SECI. SECI may agree to buy such power provided Buying Entity consents to purchase such energy. However, the SPD will not be allowed to sell energy generated prior to SCD or excess energy during any Contract Year to any other entity other than SECI (unless refused by SECI).
Appears in 5 contracts
Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
APPLICABLE TARIFF. 9.1 The SPD shall be entitled to receive the Tariff of Rs. / kWh [Insert the Tariff discovered through the bidding process conducted by SECI], fixed for the entire term of this Agreement, with effect from the SCD, for the power sold by the Buyer to the Buying Entity for the scheduled energy as reflected in the Energy AccountsREA. In case of early part-commissioning, till SCD, subject to the consent for such purchase by the Buying Utility, SECI may purchase the generation @ 75% (seventy-five per cent) of the PPA tariff. However, in case the entire Project capacity is commissioned prior to SCD, SECI may purchase energy supplied till SCD at [Insert Tariff]/kWh. In both the cases of early part or full commissioning of the Project, the Applicable Tariff for the commissioned Project shall be
9.2 Any excess generation over and above energy specified in Article 4.4.1, will be purchased by SECI at a tariff of 75% of the tariff as per Article 9.1, provided the Buying Entity consents for purchase of such excess generation. Any energy produced and flowing into the grid before SCD shall not be at the cost of SECI. SECI may agree to buy such power provided Buying Entity consents to purchase such energy. However, the SPD will not be allowed to sell energy generated prior to SCD or excess energy during any Contract Year to any other entity other than SECI (unless refused by SECI).
Appears in 3 contracts
Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
APPLICABLE TARIFF. 9.1 The SPD shall be entitled to receive the Tariff of Rs. / kWh [Insert the Tariff discovered through the bidding process conducted by SECI], fixed for the entire term of this Agreement, with effect from the SCD, for the power sold by the Buyer to the Buying Entity for the scheduled energy as reflected in the Energy Accountsaccount. In case of early part-commissioning, till SCD, subject to the consent for such purchase by the Buying Utility, SECI may purchase the generation @ 75% (seventy-five per cent) of the PPA tariff. However, in case the entire Project capacity is commissioned prior to SCD, SECI may purchase energy supplied till SCD at [Insert Tariff]/kWh. In both the cases of early part or full commissioning of the Project, the Applicable Tariff for the commissioned Project shall be
9.2 Any excess generation over and above energy specified in Article 4.4.1, will be purchased by SECI at a tariff of 75% of the tariff as per Article 9.1, provided the Buying Entity consents for purchase of such excess generation. Any energy produced and flowing into the grid before SCD shall not be at the cost of SECI. SECI may agree to buy such power provided Buying Entity consents to purchase such energy. However, the SPD will not be allowed to sell energy generated prior to SCD or excess energy during any Contract Year to any other entity other than SECI (unless refused by SECI).
9.3 Tariff Reduction shall be applicable in case of any delay as mentioned under clause nos. 4.6.1.1 and 4.6.1.2 of this PPA.
Appears in 2 contracts
APPLICABLE TARIFF. 9.1 The SPD shall be entitled to receive the Tariff of Rs. / kWh [Insert the Tariff discovered through the bidding process conducted by SECI], fixed for the entire term of this Agreement, with effect from the SCD, for the power sold by the Buyer to the Buying Entity for the scheduled energy as reflected in the Energy Accounts. In case of early part-commissioning, till SCD, subject to the consent for such purchase by the Buying Utility, SECI may purchase the generation @ 75% (seventy-five per cent) of the PPA tariff. However, in case the entire Project capacity is commissioned prior to SCD, SECI may purchase energy supplied till SCD at [Insert Tariff]/kWh. In both the cases of early part or full commissioning of the Project, the Applicable Tariff for the commissioned Project shall bebe [Insert Tariff]/kWh from and including the SCD.
9.2 Any excess generation over and above energy specified in Article 4.4.1, will be purchased by SECI at a tariff of 75% of the tariff as per Article 9.1, provided the Buying Entity consents for purchase of such excess generation. Any energy produced and flowing into the grid before SCD shall not be at the cost of SECI. SECI may agree to buy such power provided Buying Entity consents to purchase such energy. However, the SPD will not be allowed to sell energy generated prior to SCD or excess energy during any Contract Year to any other entity other than SECI (unless refused by SECI).
Appears in 1 contract
Sources: Power Purchase Agreement