Application for Completion Settlement Sample Clauses
Application for Completion Settlement. Unless otherwise agreed in the special contract terms, the contractor shall submit a completion settlement application form to the employer and the supervisor within 28 days after the project is completed and accepted, and submit complete settlement information. The requirements for the list of materials and number of copies of the completion settlement application form shall be agreed upon by the parties to the contract in the special contract terms. Unless otherwise agreed in the special contract terms, the completion settlement application form shall include the following contents:
( 1 ) Contract price for final settlement;
( 2 ) The employer has paid the contractor;
( 3 ) Quality deposit that should be withheld.
( 4 ) The employer shall pay the contractor the contract price.
Application for Completion Settlement. Unless otherwise agreed in the Special Contract Conditions, the Contractor shall submit a completion settlement application form to the Employer and the Supervisor within 28 days after the project passes the completion acceptance, along with complete settlement materials. The requirements regarding the list and number of copies of materials for the completion settlement application form shall be agreed upon by the parties to the contract in the Special Contract Conditions. Unless otherwise agreed in the Special Contract Conditions, the completion settlement application form shall include the following contents:
(1) The contract price for completion settlement;
(2) The amount already paid by the Employer to the Contractor;
(3) The quality guarantee deposit to be retained, except where a performance bond has been paid or other forms of project quality guarantee have been provided;
(4) The contract price to be paid by the Employer to the Contractor.
Application for Completion Settlement. The time limit for the Contractor to submit the completion settlement application form: Within 28 days after the project is completed, accepted and delivered.
Application for Completion Settlement. The deadline for the Contractor to submit an application for completion settlement: the General Contract Terms shall apply. The contents of the completed settlement application form: the General Contract Terms shall apply