Common use of Application for Extension of Time Clause in Contracts

Application for Extension of Time. 46.8.1. Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. The Contractor; the registration number; and Project description; 46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;

Appears in 5 contracts

Sources: Furnish and Install Agreement, Furnish and Install Agreement, Furnish and Install Agreement

Application for Extension of Time. 46.8.1. 13.8.1 Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. (a) The Contractor; the registration number; and Project description; 46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;

Appears in 3 contracts

Sources: On Call Cable Infrastructure Installation Services Agreement, Autoclave Sterilizer Maintenance and Repair Agreement, Agreement for Boilers, Heaters, Repairs and Maintenance Services

Application for Extension of Time. 46.8.113.8.1. Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. (a) The Contractor; the registration number; and Project description; 46.8.1.2. ; 13.8.1(b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1(c) Original total bid price; 13.8.1 (d) The original Contract start date and completion date;

Appears in 2 contracts

Sources: Supply and Service Agreement, Standard Construction Contract

Application for Extension of Time. 46.8.1. Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. The Contractor; the registration number; and Project description; 46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;

Appears in 1 contract

Sources: Furnish and Install Agreement

Application for Extension of Time. 46.8.1. 13.8.1 Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. The Contractor; the registration number; and Project description; 46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;

Appears in 1 contract

Sources: Construction Contract