Applications for Utility Permits. Utility Companies may apply to ADOT for utility permits and 14 other agreements and approvals to install new Utilities that would cross or longitudinally 15 occupy the Project ROW, or to modify, upgrade, relocate or expand existing Utilities within 16 the Project ROW for reasons other than to accommodate the Project. The provisions of 17 Sections 5.4.9.2 through 5.4.9.5 and Section 107.15.06.06 of the Technical Provisions 18 shall govern such Utility Company applications. Except as provided in this Section 5.4.9, 19 no work or services required of Developer, and no accommodation of new Utilities or of 20 modifications, upgrades, relocations or expansions of existing Utilities, pursuant hereto, 21 shall entitle Developer to an increase in the Contract Price, a Completion Deadline 22 adjustment or other Claim or relief.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement