Common use of Approval of Progress Payments Clause in Contracts

Approval of Progress Payments. 1. Promptly on disapproval of all or any portion of a payment request, Owner shall provide to Contractor written notice of denial identifying for each line item denied: (1) The amount withheld, (2) The Defect or reason for withholding, (3) The remedial action required to cure the Defect, and (4) Documentation needed to reestablish an obligation of Owner for payment. Within 7 Calendar Days after Contractor cures the Defect and provides appropriate documentation that is approved by Owner's Representative, Owner shall pay Contractor within 5 Calendar Days for the value of line items thus approved.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract