Asset Removal. 3.2.1. Introduction This process covers the removal of Assets, including Meters. Work carried out by the GT rather than a Meter Worker is outside scope, thus the removal of a service pipe is not considered in this process. A Meter which is being disconnected and connected as part of the same job is classed as an Asset exchange and is not covered by this process. 3.2.2. Process Map Process maps included in Annex E of the Online RGMA Data Flow Catalogue. 3.2.3. Process Steps 2.1 If required Request Asset Removal Consumer Supplier13 Unlikely to be electronic Not defined 2.2 Following 2.1 Request Asset Removal Supplier MAM ORJOB Email, IX, DTN 2.3 Within 2WDs of 2.2 Respond to Asset Removal Request MAM Supplier RRJOB Email, IX, DTN 2.4 Following 2.2 Request Asset Removal MAM Meter Worker Information contained within ORJOB Not defined 2.5 48hrs prior to Asset removal14 Pre Notification of Asset Removal MAM Supplier15 ONJOB16 Email, IX, DTN 2.6 Within 2WDs of 2.5 Respond to Pre Notification of Asset Removal Supplier MAM RNJOB Email, IX, DTN 2.7 At the time and date specified within the request in 2.4 Carry out Asset Removal Meter Worker N/A N/A N/A 13 Where the consumer has a direct commercial relationship with the MAM, the consumer may send a request directly to the MAM.
Appears in 1 contract
Asset Removal. 3.2.1. Introduction This process covers the removal of Assets, including Meters. Work carried out by the GT rather than a Meter Worker is outside scope, thus the removal of a service pipe is not considered in this process. A Meter which is being disconnected and connected as part of the same job is classed as an Asset exchange and is not covered by this process.
3.2.2. Process Map Process maps included in Annex E of the Online RGMA Data Flow Catalogue.
3.2.3. Process Steps
2.1 If required Request Asset Removal Consumer Supplier13 Supplier16 Unlikely to be electronic Not defined
2.2 Following 2.1 Request Asset Removal Supplier MAM ORJOB Email, IX, DTN
2.3 Within 2WDs of 2.2 Respond to Asset Removal Request MAM Supplier RRJOB Email, IX, DTN
2.4 Following 2.2 Request Asset Removal MAM Meter Worker Information contained within ORJOB Not defined
2.5 48hrs prior to Asset removal14 removal17 Pre Notification of Asset Removal MAM Supplier15 ONJOB16 Supplier18 ONJOB19 Email, IX, DTN
2.6 Within 2WDs of 2.5 Respond to Pre Notification of Asset Removal Supplier MAM RNJOB Email, IX, DTN
2.7 At the time and date specified within the request in 2.4 Carry out Asset Removal Meter Worker N/A N/A N/A 13 16 Where the consumer has a direct commercial relationship with the MAM, the consumer may send a request directly to the MAM.
Appears in 1 contract