Award of Subcontracts. II.10.1 If a partner has to conclude sub-contracts in order to carry out a workprogramme and they constitute costs of the workprogramme under an item of eligible direct costs in the estimated budget of the workprogramme annexed to a specific agreement, he shall seek competitive tenders from potential subcontractors and award the contract to the bid offering best value for money; in doing so he shall observe the principles of transparency and equal treatment of potential subcontractors and shall take care to avoid any conflict of interests. II.10.2 Subcontracts as referred to in paragraph 1 may be awarded only in the following cases: (a) they may only cover the execution of a limited part of the workprogramme; (b) recourse to the award of contracts must be justified having regard to the nature of the workprogramme and what is necessary for its implementation; (c) the tasks concerned must be set out in the annex of a specific agreement and the corresponding estimated costs must be set out in detail in the budget in estimated budget of the workprogramme; (d) any recourse to the award of contracts while the workprogramme is under way, if not provided for in the initial grant application, shall be subject to prior written approval by the Agency; (e) the partner shall retain sole responsibility for carrying out the workprogramme and for compliance with the provisions of the agreement. The partner must undertake to make the necessary arrangements to ensure that the subcontractor waives all rights in respect of the Agency under the framework agreement and specific agreements; (f) the partner must undertake to ensure that the conditions applicable to him under ▇▇▇▇▇▇▇▇ ▇▇.▇, ▇▇.▇, ▇▇.▇, ▇▇.▇, ▇▇.▇, ▇▇.▇, II.11 and II.20 of the framework agreement are also applicable to the sub-contractor.
Appears in 1 contract
Sources: Framework Partnership Agreement
Award of Subcontracts. II.10.1 If a partner has to conclude sub-contracts in order to carry out a workprogramme and they constitute costs of the workprogramme under an item of eligible direct costs in the estimated budget of the workprogramme annexed to a specific agreement, he shall seek competitive tenders from potential subcontractors and award the contract to the bid offering best value for money; in doing so he shall observe the principles of transparency and equal treatment of potential subcontractors and shall take care to avoid any conflict of interests.
II.10.2 Subcontracts as referred to in paragraph 1 may be awarded only in the following cases:
(a) they may only cover the execution of a limited part of the workprogramme;
(b) recourse to the award of contracts must be justified having regard to the nature of the workprogramme and what is necessary for its implementation;
(c) the tasks concerned must be set out in the annex of a specific agreement and the corresponding estimated costs must be set out in detail in the budget in estimated budget of the workprogramme;
(d) any recourse to the award of contracts while the workprogramme is under way, if not provided for in the initial grant application, shall be subject to prior written approval by the Agency;
(e) the partner shall retain sole responsibility for carrying out the workprogramme and for compliance with the provisions of the agreement. The partner must undertake to make the necessary arrangements to ensure that the subcontractor waives all rights in respect of the Agency under the framework agreement and specific agreements;and
(f) the partner must undertake to ensure that the conditions applicable to him under ▇▇▇▇▇▇▇▇ ▇▇.▇, ▇▇.▇, ▇▇.▇, ▇▇.▇, ▇▇.▇, ▇▇.▇, II.11 and II.20 of the framework agreement are also applicable to the sub-contractor.