Before Commencement of Construction. 5.1.1 Prior to commencement of any construction activity, the Concessionaire shall finalise an implementation plan for the Project (“Implementation Plan”) in consultation with the Independent Consultant. The Implementation Plan shall, inter alia, include: (a) A detailed schedule of implementation for putting up and operationalizing the Project Facilities, which shall specify at least four major milestones; (b) The Critical Path Method (CPM)/Programme Evaluation and Review Technique (PERT) charts or similar activity planning technique/ method for monitoring. This would cover all stages/ aspects of implementation of the Project Facilities including design and engineering, procurement of materials and equipment, installation, construction and testing;
Appears in 1 contract
Sources: Concession Agreement
Before Commencement of Construction. 5.1.1 Prior to commencement of any construction activity, the Concessionaire shall finalise an implementation plan for the Project (“Implementation Plan”) in consultation with the Independent Consultant. The Implementation Plan shall, inter alia, include:
(a) A detailed schedule of implementation for putting up and operationalizing operationalising the Project Facilities, which shall specify at least four major milestones;
(b) The Critical Path Method (CPM)/Programme Evaluation and Review Technique (PERT) charts or similar activity planning technique/ method for monitoring. This would cover all stages/ aspects of implementation of the Project Facilities including design and engineering, procurement of materials and equipment, installation, construction and testing;
Appears in 1 contract
Sources: Concession Agreement