Behind The Meter Generation. AEP shall cooperate with PJM and parties operating generators connected behind load metering, such that PJM will receive such generator output meter information, as it is required, for the following two categories of generators operating behind the meter within the AEP Zone: 4.4.1 Generators that do not participate in the PJM Markets: The generating party shall provide AEP Transmission Settlements East, each month by the 5th working day after the end of the month, a data file containing the hourly unit or plant kWh output. Alternatively, Customer may provide AEP access to the meter to download the generator output meter data using dial-up remote interrogation. 4.4.2 Generators that do participate in the PJM Markets: The generating party shall provide real-time unit or plant output data required by PJM via an Inter-Control Center Protocol (“ICCP”) data link to AEP. In addition, Customer shall permit AEP to remotely interrogate the meters to obtain integrated hourly meter data each day. AEP shall provide the generation data obtained from the generating party to PJM through the PJM eSuites or EMS application within the PJM time requirements, as applicable.
Appears in 2 contracts
Sources: Facilities Agreement, Facilities Agreement
Behind The Meter Generation. AEP shall cooperate with PJM and parties operating generators connected behind load metering, such that PJM will receive such generator output meter information, information as it is required, for the following two categories of generators operating behind the meter within the AEP Zone:
4.4.1 Generators that do not participate in the PJM Markets: The generating party shall provide AEP Transmission Settlements Eastprovide, each month by the 5th working day after the end of the month, a data file containing the hourly unit or plant kWh output. Alternatively, Customer may provide AEP access to the meter to download the generator output meter data using dial-up remote interrogation.
4.4.2 Generators that do participate in the PJM Markets: The generating party shall provide real-time unit or plant output data required by PJM via an Inter-Control Center Protocol (“ICCP”) data link to AEP. In addition, Customer shall permit AEP to remotely interrogate the meters to obtain integrated hourly meter data each day. AEP shall provide the generation data obtained from the generating party to PJM through the PJM eSuites or EMS application within the PJM time requirements, as applicable.
Appears in 1 contract
Sources: Facilities Agreement