BREAK CLAUSE. 50.1 Where stipulated in the Contract Particulars, the Council shall have the right to terminate the Contract at any time by giving written notice (of not less than the period specified in the Contract Particulars) to the Supplier 50.2 Where the Council exercises its right to terminate the Contract under clause 50.1, the Supplier shall only be entitled to payment for Services duly rendered up to the date of termination and the Council shall incur no liability to the Supplier in respect of any other losses whatsoever whether: 50.2.1 loss of future profits; 50.2.2 redundancy or Sub-Contractor breakage costs; or 50.2.3 any other costs whatsoever incurred by the Supplier as a consequence of such termination.
Appears in 2 contracts
Sources: Supplier Agreement, Supplier Agreement
BREAK CLAUSE. 50.1
51.1 Where stipulated in the Contract Particulars, the Council shall have the right to terminate the Contract at any time by giving written notice (of not less than the period specified in the Contract Particulars) to the SupplierContractor
50.2 51.2 Where the Council exercises its right to terminate the Contract under clause 50.151.1, the Supplier Contractor shall only be entitled to payment for Services duly rendered up to the date of termination and the Council shall incur no liability to the Supplier Contractor in respect of any other losses whatsoever whether:
50.2.1 51.2.1 loss of future profits;
50.2.2 51.2.2 redundancy or Subsub-Contractor contractor breakage costs; or
50.2.3 51.2.3 any other costs whatsoever incurred by the Supplier Contractor as a consequence of such termination.
Appears in 2 contracts
Sources: Services Agreements, Services Agreement
BREAK CLAUSE. 50.1 51.1 Where stipulated in the Contract Particulars, the Council shall have the right to terminate the Contract at any time by giving written notice (of not less than the period specified in the Contract Particulars) to the SupplierContractor
50.2 51.2 Where the Council exercises its right to terminate the Contract under clause 50.151.1, the Supplier Contractor shall only be entitled to payment for Services duly rendered up to the date of termination and the Council shall incur no liability to the Supplier Contractor in respect of any other losses whatsoever whether:
50.2.1 51.2.1 loss of future profits;
50.2.2 51.2.2 redundancy or Subsub-Contractor contractor breakage costs; or
50.2.3 51.2.3 any other costs whatsoever incurred by the Supplier Contractor as a consequence of such termination.
Appears in 2 contracts
Sources: Contract Agreement, Services Agreement
BREAK CLAUSE.
50.1 Where stipulated in the Contract Particulars, the Council shall have the right to terminate the Contract at any time by giving written notice (of not less than the period specified in the Contract Particulars) to the SupplierSupplier.
50.2 Where the Council exercises its right to terminate the Contract under clause 50.1, the Supplier shall only be entitled to payment for Services duly rendered up to the date of termination and the Council shall incur no liability to the Supplier in respect of any other losses whatsoever whether:
50.2.1 loss of future profits;
50.2.2 redundancy or Sub-Contractor breakage costs; or
50.2.3 any other costs whatsoever incurred by the Supplier as a consequence of such termination.
Appears in 1 contract
Sources: Supplier Agreement
BREAK CLAUSE. 50.1 54.1 Where stipulated in the Contract Particulars, the Council shall have the right to terminate the Contract at any time by giving written notice (of not less than the period specified in the Contract Particulars) to the SupplierContractor
50.2 54.2 Where the Council exercises its right to terminate the Contract under clause 50.154.1, the Supplier Contractor shall only be entitled to payment for Services duly rendered up to the date of termination and the Council shall incur no liability to the Supplier Contractor in respect of any other losses whatsoever whether:
50.2.1 54.2.1 loss of future profits;
50.2.2 54.2.2 redundancy or Subsub-Contractor contractor breakage costs; or
50.2.3 54.2.3 any other costs whatsoever incurred by the Supplier Contractor as a consequence of such termination.