Build. 1.5.1.1. During the Setup phase (as defined in the SOW), Provider will invest in the System design (as set forth in the SOW), importing the System, set-up, training, supplying raw material, install and check the system and more (together the “BUILD”) as stipulated in Appendix C - ▇▇▇▇ of Materials and Prices (the “BOM”) to BUILD the Project. It is noted that Provider’s estimate of the initial investment for the Build phase is 8,000,000 US$. 1.5.1.2. The implementation plan for this Build phase is specified in the PIP.
Appears in 2 contracts
Sources: Build, Operate and Transfer (Bot) Agreement (On Track Innovations LTD), Build, Operate and Transfer (Bot) Agreement (On Track Innovations LTD)