Common use of Burial Clause in Contracts

Burial. Company shall bury or have buried its Pipeline at least four feet (4′) deep except underneath public roads that are on the Public Rights-of-Way. Underneath public roads on the Public Rights-of- Way, below-ground parts of the Pipeline shall be at least seven feet (7′) below the lowest point in such road pavement. When the Pipeline cannot be bored, during backfill of the Pipeline excavation, “Buried Pipeline” warning tape shall be buried between 12” and 24” inches above the Pipeline to warn future excavators of the presence of the Pipeline.

Appears in 2 contracts

Sources: Public Right of Way Use Agreement, Public Right of Way Use Agreement