Capacity Assessment. (a) Subject to clause 9.3(c), Aurizon Network must, within six months after the completion and commissioning of an Expansion referred to in clause 9.2, undertake an assessment (Capacity Assessment) in respect of that Expansion to determine, in accordance with clause 9.3(b), the change in Existing Capacity (Capacity Change) for each Segment of the Expansion. (b) For the purposes of clause 9.3(a), the Capacity Change for each Segment of an Expansion is the amount which is: (i) the Existing Capacity of the Segment of the Expansion as a result of the Expansion being undertaken; less (ii) the Existing Capacity of the Segment of the Expansion if the Expansion had not been undertaken, using consistent Operating Parameters.
Appears in 4 contracts
Sources: Access Holder Access Agreement, Operator Access Agreement, Access Agreement
Capacity Assessment. (a) Subject to clause 9.3(c7.3(c), Aurizon Network must, within six months after the completion and commissioning of an Expansion referred to in clause 9.27.2, undertake an assessment (Capacity Assessment) in respect of that Expansion to determine, in accordance with clause 9.3(b7.3(b), the change in Existing Capacity (Capacity Change) for each Segment of the Expansion.
(b) For the purposes of clause 9.3(a7.3(a), the Capacity Change for each Segment of an Expansion is the amount which is:
(i) the Existing Capacity of the Segment of the Expansion as a result of the Expansion being undertaken; less
(ii) the Existing Capacity of the Segment of the Expansion if the Expansion had not been undertaken, using consistent Operating Parameters.
Appears in 1 contract
Sources: End User Access Agreement