Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery. b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items. c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records). d. The Information provided on the CofC shall include: (1) Contractor’s name and address; (2) Contractor unique CofC number; (3) Contract number and where applicable Contract amendment number; (4) details of any approved concessions; (5) acquirer name and organisation; (6) Delivery address; (7) Contract Item Number from Schedule 2 (Schedule of Requirements); (8) description of Contractor Deliverable, including part number, specification and configuration status; (9) NATO Stock Number (NSN) (where allocated); (10) identification marks, batch and serial numbers in accordance with the Specification; (11) quantities; (12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented. e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.
Appears in 19 contracts
Sources: Contract, Contract, Provision of Typhoon Mids Bu2 Servicing Support
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 2625.
Appears in 12 contracts
Sources: Contract, Contract for Anti Vibration Systems, Contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Deliverydelivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "’Certificate of Conformity" ’ in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition condition 17 (Contractor’s Contractors Records).
d. The Information information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information information called for at clause 26.
Appears in 3 contracts
Sources: Contract for Repair and Refurbishment Services, Terms and Conditions, Supply Agreement
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s 's Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s 's Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s 's name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification; (11)quantities;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.
Appears in 2 contracts
Sources: Contract for the Provision of Design and Integration Partner, Production and Installation Agreement
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. . Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. . The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. . The Information provided on the CofC shall include:
(1) : Contractor’s name and address;
(2) ; Contractor unique CofC number;
(3) ; Contract number and where applicable Contract amendment number;
(4) ; details of any approved concessions;
(5) ; acquirer name and organisation;
(6) ; Delivery address;
(7) ; Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) ; description of Contractor Deliverable, including part number, specification and configuration status;
(9) ; NATO Stock Number (NSN) (where allocated);
(10) ; identification marks, batch and serial numbers in accordance with the Specification;
(11) ; quantities;
(12) ; a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.
Appears in 2 contracts
Sources: Support Contract, Contract for Boiler Design, Supply & Install
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Deliverydelivery, and one copy shall be provided to the Consignee upon Delivery.
b. . Each CofC should include the wording "’Certificate of Conformity" ’ in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. . The Contractor shall consider the CofC to be a record in accordance with Condition condition 17 (Contractor’s Contractors Records).
d. ) The Information information provided on the CofC shall include:
(1) : Contractor’s name and address;
(2) ; Contractor unique CofC number;
(3) ; Contract number and where applicable Contract amendment number;
(4) ; details of any approved concessions;
(5) ; acquirer name and organisation;
(6) ; Delivery address;
(7) ; Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) ; description of Contractor Deliverable, including part number, specification and configuration status;
(9) ; NATO Stock Number (NSN) (where allocated);
(10) ; identification marks, batch and serial numbers in accordance with the Specification;
(11) ; quantities;
(12) ; a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.
Appears in 2 contracts
Sources: Supply Agreement, Supply Agreement
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specificationquantities;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. d. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 2625.
Appears in 2 contracts
Sources: MHC Autonomy Software Integration & Support, Contractor Logistics Support Contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s 's Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s 's Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s 's name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.
Appears in 2 contracts
Sources: Purchase Agreement, Purchase Agreement
Certificate of Conformity.
a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.
Appears in 2 contracts
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (the Schedule of Requirements) Requirements and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (the Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (the Schedule of Requirements) Requirements and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 2626.d. The Contractor shall ensure that this Information is available to the Authority through the supply chain upon request in accordance with Condition 17 (Contractor Records).
Appears in 1 contract
Sources: Contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.require
Appears in 1 contract
Sources: Contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;.
(2) Contractor unique CofC number;.
(3) Contract number and where applicable Contract amendment number;.
(4) details of any approved concessions;.
(5) acquirer name and organisation;.
(6) Delivery address;.
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);.
(8) description of Contractor Deliverable, including part number, specification and configuration status;.
(9) NATO Stock Number (NSN) (where allocated);.
(10) identification marks, batch and serial numbers in accordance with the Specification;.
(11) quantities;.
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.clause
Appears in 1 contract
Sources: Supply and Support Contract
Certificate of Conformity. a. a) Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. b) Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. c) The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. d) The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. e) Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 2625.
Appears in 1 contract
Sources: Support Contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s 's Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s 's Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s 's name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.clause
Appears in 1 contract
Sources: Contract for Simulator Support
Certificate of Conformity. a. Applicable DEFCONs: DEFCON 609 (Edn 06/14) – Contractor’s Records DEFCON 627 (Edn 12/10) – Quality Assurance – Requirement for a Certificate of Conformity (CoC)
8.1. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofCCof C) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC Cof C shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification8.2. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (appropriate Contractor’s Records).
d. 8.2.1. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details Details of any approved concessions;
(5) acquirer Acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description Description of Contractor Deliverable, including part number, specification Specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification Identification marks, batch and serial numbers in accordance with the Specification;
(1110) quantitiesQuantities;
(1211) a A signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions.
8.3. Exceptions or additions to the above are to be documented.
e. 8.4. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract this requirement. The Contractor shall ensure that this Information is available to the requirement for Authority through the Information called for at clause 26.supply chain, upon request as part of the Contractor’s Records
Appears in 1 contract
Sources: Contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.Information
Appears in 1 contract
Sources: Defence Medical Services Contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 2625.
a. The Contractor shall ensure that this Information is available to the Authority through the supply chain upon request in accordance with Condition 17 (Contractor Records).
Appears in 1 contract
Certificate of Conformity. a. Where required in Schedule 3 (Contract Data Sheet) the Contractor shall provide a Certificate of Conformity (CofC) in accordance with Schedule 2 (Schedule of Requirements) and any applicable Quality Plan. One copy of the CofC shall be sent to the Authority’s Representative (Commercial) upon Delivery, and one copy shall be provided to the Consignee upon Delivery.
b. Each CofC should include the wording "Certificate of Conformity" in the title of the document to allow for easy identification. One CofC is to be used per NSN/part number; a CofC must not cover multiple line items.
c. The Contractor shall consider the CofC to be a record in accordance with Condition 17 (Contractor’s Records).
d. The Information provided on the CofC shall include:
(1) Contractor’s name and address;
(2) Contractor unique CofC number;
(3) Contract number and where applicable Contract amendment number;
(4) details of any approved concessions;
(5) acquirer name and organisation;
(6) Delivery address;
(7) Contract Item Number from Schedule 2 (Schedule of Requirements);
(8) description of Contractor Deliverable, including part number, specification and configuration status;
(9) NATO Stock Number (NSN) (where allocated);
(10) identification marks, batch and serial numbers in accordance with the Specification; quantities;
(11) quantities;
(12) a signed and dated statement by the Contractor that the Contractor Deliverables comply with the requirements of the Contract and approved concessions. Exceptions or additions to the above are to be documented.
e. Where Schedule 2 (Schedule of Requirements) and any applicable Quality Plan require demonstration of traceability and design provenance through the supply chain the Contractor shall include in any relevant subcontract the requirement for the Information called for at clause 26.
Appears in 1 contract