Change estimate. The Contractor shall, within a maximum of three (3) Working days from receipt of a written request for a change, submit a study of potential risk and change consequences, as well as a price estimate. In the event of a request for larger changes, the parties shall agree an extension of the deadline with such number of days as is deemed to be reasonable. At a minimum, the study shall include the following: a) description of the change b) description of the scope of work that needs to be carried out as a result of the change, and the time required for such work c) impact on other functional and Non-functional requirements, and Other components of the deliverables d) impact on Estimated total cost e) impact on Project and milestone plan, and ReleasePlan, cf. clause 3.6 f) requirements concerning the Customer's participation g) changes to Test plans and test criteria h) consequences for future maintenance of the deliverables Documented costs in connection with the preparation of change estimates are carried by the Customer in accordance with the prices and terms applicable to supplementary work, cf. Appendix 7. If the preparation of a change estimate does in itself necessitate changes to the milestone plan, the Contractor may request that the plan be adjusted. The Contractor may propose changes and draw up a change estimate on its own initiative. The Contractor will only receive reimbursement of its costs if the Customer accepts the change proposal and the estimate, and sends a change order.
Appears in 1 contract
Sources: Agile Software Development Agreement
Change estimate. The Contractor shall, within a maximum of three (3) Working days from receipt of a written request for a change, submit a study of potential risk and change consequences, as well as a price estimate. In the event of a request for larger changes, the parties shall agree an extension of the deadline with such number of days as is deemed to be reasonable. At a minimum, the study shall include the following:
a) description of the change
b) description of the scope of work that needs to be carried out as a result of the change, and the time required for such work
c) impact on other functional and Non-functional requirements, and Other components of the deliverables
d) impact on Estimated total cost
e) impact on Project and milestone plan, and ReleasePlanRelease Plan, cf. clause 3.6
f) requirements concerning the Customer's participation
g) changes to Test plans and test criteria
h) consequences for future maintenance of the deliverables Documented costs in connection with the preparation of change estimates are carried by the Customer in accordance with the prices and terms applicable to supplementary work, cf. Appendix 7. If the preparation of a change estimate does in itself necessitate changes to the milestone plan, the Contractor may request that the plan be adjusted. The Contractor may propose changes and draw up a change estimate on its own initiative. The Contractor will only receive reimbursement of its costs if the Customer accepts the change proposal and the estimate, and sends a change order.