Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the Authority (“Change Order”).
Appears in 7 contracts
Sources: Short Form Construction Contract, Short Form Construction Contract, Short Form Construction Contract
Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the Authority (“Change Order”)City.
Appears in 7 contracts
Sources: Maintenance Agreement, Short Form Construction Contract, Short Form Construction Contract
Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the Authority City (“Change Order”).
Appears in 3 contracts
Sources: Construction Contract, Construction Contract, Short Form Construction Contract
Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the Authority (“Change Order”)District.
Appears in 1 contract
Sources: Construction Contract
Change in Scope of Work. 6.1. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition addition, or deletion is approved in advance and in writing by a valid valid, mutually-agreed change order or amendment executed by the Authority (“Change Order”)Parties.
Appears in 1 contract
Sources: Design and Construction Contract
Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the Authority (“Change Order”)Commission.
Appears in 1 contract
Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the Authority (“Change Order”)Town.
Appears in 1 contract
Sources: Construction Contract