Change Order Certification. 17.9.1. All Change Orders and CORs shall include the following certification by the Contractor. The Parties acknowledged that if a Change Order is approved that does not include this language, that Change Order shall be deemed to include this certification language:
Appears in 2 contracts
Sources: Site Lease, Site Lease
Change Order Certification. 17.9.1. All Change Orders and CORs shall include the following certification by the Contractor. The Parties acknowledged that if a Change Order is approved that does not include this language, that Change Order shall be deemed to include this certification language:: It is expressly understood that the value of the extra Work or changes expressly includes any and all of the Contractor’s costs and expenses, both direct and indirect, resulting from additional time required on the Project or resulting from delay to the Project. Any costs, expenses, damages, or time extensions not included are deemed waived.
Appears in 1 contract
Sources: Site Lease