Common use of Change Order Procedures Clause in Contracts

Change Order Procedures. 7.3.1 When requested by the City’s Representative, the Design Build Entity shall provide promptly, but in no event longer than seven (7) days from the date of the request, a Cost Proposal setting forth the Design Build Entity’s proposed adjustments of the Contract Price and/or the Contract Time, if any, for performing the proposed change in the Scope of Work. Adjustments of the Contract Price resulting from Extra Work and/or deductive work shall be determined using one of the methods described in Article 7. Adjustments of the Contract Time shall be subject to the provisions in Article 8.