Change Order Procedures. 1. Either Party may request a Change Order but all Change Orders must be in writing and prepared by ACCESS. ACCESS may, at the discretion of ACCESS, charge a reasonable fee for investigating, preparing or initiating a Change Order at CUSTOMER's request. 2. Change Order requests will be processed as soon as is reasonably possible. The change will be evaluated and any project impact will be identified. The cost, scope, and schedule impact, if any, of the change will be analyzed and documented. The change impact will then be processed for CUSTOMER authorization or closure. 3. All Change Orders will be in the form attached hereto as Exhibit 1E, and will be signed by the appointed representative for each Party 4. Change Orders will include the following: (a) A description of any additional work to be performed and/or any changes to the performance required of either Party. (b) A statement of the impact of the work or changes on the Services, the Deliverables, or other requirements of the Agreement. (c) The estimated timetable to complete the work specified in the Change Order and the impact, if any, on the delivery schedule, pricing and payments. (d) Specific individuals with management or coordination responsibilities. (e) The documentation to be modified or supplied as part or the work. 5. All Change Orders must be mutually agreed by the Parties. ACCESS will not commence or perform work on any such modification prior to execution and receipt of a Change Order in the form of Exhibit 1E. EXHIBIT 1E CHANGE ORDER FOR TECHNICAL SERVICES AGREEMENT BETWEEN ACCESS AND , DATED CHANGE ORDER NUMBER This Change Order Form is an exhibit to the Technical Services Agreement, dated by and between ACCESS and ("CUSTOMER"), which is incorporated herein by reference. By executing the Agreement the Parties agree to be bound by the terms and conditions of the Technical Services Agreement. This Change Order describes the work that shall be completed under this Agreement, and the relevant fees and expenses related thereto. In consideration for compensation as detailed in this Agreement, ACCESS agrees to provide Technical services to CUSTOMER, as follows: 1. Describe services or changes requested [attach additional pages if necessary]. 2. Modifications, clarifications or supplements to description of services or changes requested in paragraph 1 above, if any [attach additional pages if necessary]: 3. Assignment of necessary ACCESS personnel and resources [attach additional pages if necessary]: 4. Impact on price, delivery schedule, payment schedule, Deliverables, and Services [attach additional pages if necessary]: a) Price: b) Delivery Schedule and Payment Schedule:
Appears in 1 contract
Sources: Technical Services Agreement
Change Order Procedures. 1. Either Party may request a Change Order but all Change Orders must be in writing and prepared by ACCESS. ACCESS may, at the discretion of ACCESS, charge a reasonable fee for investigating, preparing or initiating a Change Order at CUSTOMER's request.
2. Change Order requests will be processed as soon as is reasonably possible. The change will be evaluated and any project impact will be identified. The cost, scope, and schedule impact, if any, of the change will be analyzed and documented. The change impact will then be processed for CUSTOMER authorization or closure.
3. All Change Orders will be in the form attached hereto as Exhibit 1E, and will be signed by the appointed representative for each Party
4. Change Orders will include the following:
(a) A description of any additional work to be performed and/or any changes to the performance required of either Party.
(b) A statement of the impact of the work or changes on the Services, the Deliverables, or other requirements of the Agreement.
(c) The estimated timetable to complete the work specified in the Change Order and the impact, if any, on the delivery schedule, pricing and payments.
(d) Specific individuals with management or coordination responsibilities.
(e) The documentation to be modified or supplied as part or the work.
5. All Change Orders must be mutually agreed by the Parties. ACCESS will not commence or perform work on any such modification prior to execution and receipt of a Change Order in the form of Exhibit 1E. EXHIBIT 1E CHANGE ORDER FOR TECHNICAL SERVICES AGREEMENT BETWEEN ACCESS AND , DATED CHANGE ORDER NUMBER This If either Party proposes a Change Order Form which, in ACCESS' judgment, represents a material change in the Services or Deliverables and such Change Order remains outstanding for thirty (30) days or is an exhibit rejected by CUSTOMER, ACCESS will have the right to terminate the affected Statement of Work pursuant to the termination provisions set forth in the Technical Services Agreement, dated by and between ACCESS and ("CUSTOMER"), which is incorporated herein by reference. By executing reserves the Agreement the Parties agree right to be bound by the terms and conditions of the Technical Services Agreement. This Change Order describes the work that shall be completed under this Agreement, and the relevant ▇▇▇▇ CUSTOMER for fees and expenses related thereto. In consideration for compensation as detailed incurred in this Agreement, ACCESS agrees to provide Technical services to CUSTOMER, as follows:
1. Describe services or changes requested [attach additional pages if necessary]good faith.
26. ModificationsIf applicable, clarifications or supplements to description a new Statement of services or changes requested Work may be issued in paragraph 1 above, if any [attach additional pages if necessary]:
3. Assignment lieu of necessary ACCESS personnel and resources [attach additional pages if necessary]:
4. Impact on price, delivery schedule, payment schedule, Deliverables, and Services [attach additional pages if necessary]:
a) Price:
b) Delivery Schedule and Payment Schedule:a Change Order.
Appears in 1 contract
Sources: Technical Services Agreement
Change Order Procedures. 1. Either Party may request a Change Order but all Change Orders must be in writing and prepared by ACCESS. ACCESS may, at the discretion of ACCESS, charge a reasonable fee for investigating, preparing or initiating a Change Order at CUSTOMER's request.
2. Change Order requests will be processed as soon as is reasonably possible. The change will be evaluated and any project impact will be identified. The cost, scope, and schedule impact, if any, of the change will be analyzed and documented. The change impact will then be processed for CUSTOMER authorization or closure.
3. All Change Orders will be in the form attached hereto as Exhibit 1E, and will be signed by the appointed representative for each Party
4. Change Orders will include the following:
(a) A description of any additional work to be performed and/or any changes to the performance required of either Party.
(b) A statement of the impact of the work or changes on the Services, the Deliverables, or other requirements of the Agreement.
(c) The estimated timetable to complete the work specified in the Change Order and the impact, if any, on the delivery schedule, pricing and payments.
(d) Specific individuals with management or coordination responsibilities.
(e) The documentation to be modified or supplied as part or the work.
5. All Change Orders must be mutually agreed by the Parties. ACCESS will not commence or perform work on any such modification prior to execution and receipt of a Change Order in the form of Exhibit 1E. EXHIBIT 1E CHANGE ORDER FOR TECHNICAL SERVICES AGREEMENT BETWEEN ACCESS AND , DATED CHANGE ORDER NUMBER This Change Order Form is an exhibit to the Technical Services Agreement, dated by and between ACCESS and ("CUSTOMER"), which is incorporated herein by reference. By executing the Agreement the Parties agree to be bound by the terms and conditions of the Technical Services Agreement. This Change Order describes the work that shall be completed under this Agreement, and the relevant fees and expenses related thereto. In consideration for compensation as detailed in this Agreement, ACCESS agrees to provide Technical services to CUSTOMER, as follows:
1. Describe services or changes requested [attach additional pages if necessary].
2. Modifications, clarifications or supplements to description of services or changes requested in paragraph 1 above, if any [attach additional pages if necessary]:
3. Assignment of necessary ACCESS personnel and resources [attach additional pages if necessary]:
4. Impact on price, delivery schedule, payment schedule, Deliverables, and Services [attach additional pages if necessary]:
a) Price:
b) Delivery Schedule and Payment Schedule:
Appears in 1 contract
Sources: Technical Services Agreement
Change Order Procedures. 1. Either Party may request a Change Order but all Change Orders must be in writing and prepared by ACCESS. ACCESS may, at the discretion of ACCESS, charge a reasonable fee for investigating, preparing or initiating a Change Order at CUSTOMER's request.
2. Change Order requests will be processed as soon as is reasonably possible. The change will be evaluated and any project impact will be identified. The cost, scope, and schedule impact, if any, of the change will be analyzed and documented. The change impact will then be processed for CUSTOMER authorization or closure.
3. All Change Orders will be in the form attached hereto as Exhibit 1E, and will be signed by the appointed representative for each Party
4. Change Orders will include the following:
(a) A description of any additional work to be performed and/or any changes to the performance required of either Party.
(b) A statement of the impact of the work or changes on the Services, the Deliverables, or other requirements of the Agreement.
(c) The estimated timetable to complete the work specified in the Change Order and the impact, if any, on the delivery schedule, pricing and payments.
(d) Specific individuals with management or coordination responsibilities.
(e) The documentation to be modified or supplied as part or the work.
5. All Change Orders must be mutually agreed by the Parties. ACCESS will not commence or perform work on any such modification prior to execution and receipt of a Change Order in the form of Exhibit 1E. EXHIBIT 1E CHANGE ORDER FOR TECHNICAL SERVICES AGREEMENT BETWEEN ACCESS AND , DATED CHANGE ORDER NUMBER This Change Order Form is an exhibit to the Technical Services Agreement, dated by and between ACCESS and ("CUSTOMER"), which is incorporated herein by reference. By executing the Agreement the Parties agree to be bound by the terms and conditions of the Technical Services Agreement. This Change Order describes the work that shall be completed under this Agreement, and the relevant fees and expenses related thereto. In consideration for compensation as detailed in this Agreement, ACCESS agrees to provide Technical services to CUSTOMER, as follows:dated
1. Describe services or changes requested [attach additional pages if necessary].
2. Modifications, clarifications or supplements to description of services or changes requested in paragraph 1 above, if any [attach additional pages if necessary]:
3. Assignment of necessary ACCESS personnel and resources [attach additional pages if necessary]:
4. Impact on price, delivery schedule, payment schedule, Deliverables, and Services [attach additional pages if necessary]:
a) Price:
b) Delivery Schedule and Payment Schedule:
Appears in 1 contract
Sources: Technical Services Agreement