Common use of Changed Conditions Clause in Contracts

Changed Conditions. 42.1. Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or

Appears in 5 contracts

Sources: Construction Management Contract, Construction Management Services Agreement, Project Construction Management Contract

Changed Conditions. 42.1. Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents Documents, or

Appears in 2 contracts

Sources: Construction Management Contract, Construction Management Contract

Changed Conditions. 42.1. Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or

Appears in 1 contract

Sources: Project Design Build Contract

Changed Conditions. 42.1. ‌ 38.1 Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or

Appears in 1 contract

Sources: Construction Contract

Changed Conditions. 42.1. 42.1 Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or

Appears in 1 contract

Sources: Construction Management Agreement