Changes in Key Personnel. The ▇▇▇▇ Contractor shall assign the key personnel identified in the ▇▇▇▇ Contractor’s Proposal to this Project. The ▇▇▇▇ Contractor shall submit the names and qualifications of proposed replacement key personnel to CPRA’s Project Manager 30 Calendar Days in advance of any replacement of any key personnel. CPRA's Project Manager will have the authority to either reject or approve any proposed replacement key personnel in his sole discretion. The ▇▇▇▇ Contractor shall change key personnel only upon receipt of a written consent from CPRA’s Project Manager. CPRA’s Project Manager may require written justification from the ▇▇▇▇ Contractor explaining the replacement of any key personnel.
Appears in 2 contracts
Sources: Contract for Construction Management at Risk (Cmar) Construction Services, Contract for Construction Management at Risk (Cmar) Construction Services