Common use of Changes in the Scope of Work Clause in Contracts

Changes in the Scope of Work. Changes in the contractual scope of work shall be preceded by a duly executed Change Order or Contract Modification Worksheet itemizing any change in the Contract sum or terms and conditions. a. Any change in the scope of work, Contract Modification, or Change Order amount must be submitted on Metra’s Contract Modification Worksheet and negotiated with Metra. All Change Orders must be approved by Metra prior to execution. Final authority will reside with the Executive Director. b. On Contracts less than $1,000,000.00, the Contractor’s profit added to the subcontractor’s itemized statement cannot exceed five (5) percent and overhead cannot exceed ten (10) percent. On Contracts over $1,000,000.00, the Contractor’s profit added to the subcontractor’s itemized statement cannot exceed five (5) percent and overhead cannot exceed five (5) percent.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract