Changes to the Contract Price Sample Clauses

Changes to the Contract Price. (a) Except as set forth in Section 9.5.3(b), with respect to any Change Order required to be issued to increase the Contract Price as a result of an event described in Section 9.5.1, unless the Parties agree otherwise in writing, such Change Order will, on a retrospective basis, increase the Contract Price by an amount equal to the Direct Costs incurred by Contractor solely in connection with such event, plus a ▇▇▇▇-up. The ▇▇▇▇-up is not to exceed percent ( %) in the aggregate, including all Subcontractor and Contractor ▇▇▇▇-ups solely in connection with such Change. (b) In no event will Contractor be entitled to payment for Direct Costs hereunder to the extent that such costs would have occurred notwithstanding such event, due to the concurrent fault, actions or omissions of Contractor or its Subcontractors. (c) For purposes hereof, “Direct Costs” shall mean only the actual, documented costs that are directly incurred by Contractor as a result of the event giving rise to the Change Order for the following items: (i) compensation for labor utilized and in the direct employ of Contractor at the Project Site, at the rates as set forth in Exhibit B-4; (ii) cost of materials and permanent equipment; (iii) payments properly made by Contractor to Subcontractors; (iv) rental charges of necessary machinery and equipment (but excluding hand tools) used at the Project Site;
Changes to the Contract Price. To the extent that the Party requesting the Change reasonably demonstrates that such Change will affect the basis for the Contract Price (taking into consideration implementation of reasonable mitigation of such effect), then System Owner will issue the Change Order including an equitable change in the Contract Price. System Owner shall determine, in its sole discretion, whether such change in the Contract Price shall be based (a)on a lump sum adjustment or (b) on the documented change in Supplier’s actual costs, reasonably incurred, associated with the Change.
Changes to the Contract Price. Effect of data and design clarification Impact of procurement decisions Determining the cost effect of changes
Changes to the Contract Price. Except as set forth in Section 9.5.3(b), with respect to any Change Order required to be issued to increase the Contract Price as a result of an event described in Section 9.5.1, unless the Parties agree otherwise in writing, such Change Order will, on a retrospective basis, increase the Contract Price by an amount equal to the Direct Costs incurred by Contractor solely in connection with such event, plus a ▇▇▇▇-up. The ▇▇▇▇-up is not to exceed ______ percent (__%) in the aggregate, including all Subcontractor and Contractor ▇▇▇▇-ups solely in connection with such Change. In no event will Contractor be entitled to payment for Direct Costs hereunder to the extent that such costs would have occurred notwithstanding such event, due to the concurrent fault, actions or omissions of Contractor or its Subcontractors.
Changes to the Contract Price. Any increase (or decrease, in the context of a Change Order decreasing the amount of Work to be performed) in the Contract Price, if any, resulting from a Change shall be determined and shall be payable by (or due to) Owners as follows: (i) [***] (ii) if the Parties do not agree, then until such matter is resolved and the payment for such Change is determined pursuant to Article 27 [***];
Changes to the Contract Price. Within five (5) Business Days of submission of a Change Order Notice under Section 19.2.1, or within ten (10) Business Days after submission of a Change Order Request under Section 19.2.2, the Contractor shall prepare and submit, on an Open Book basis, an analysis of the impact of the Change on the Cost Element for the System, Facility, or Project, as the context may require. Contractor shall supplement this analysis on an Open Book basis with such other information as Owner may reasonably require. The amount of an increase or decrease in the Cost Element and Fee Element, if any, resulting from a Change will be determined and will be included in the Change Order as follows: 19.14.1 in a lump sum amount proposed by Contractor and accepted by Owner; or 19.14.2 if Owner does not accept the lump sum amount proposed by Contractor, by unit prices agreed upon by the Parties; or 19.14.3 if neither of the methods set forth in Sections 19.14.1 or 19.
Changes to the Contract Price as a result of a change in the Work shall be subject to the following limitations: 4.6.2.1 Under no circumstances shall a change in the Work modify the Contract Price unless Owner shall have executed a Change Order or an Owner Directive with respect to such change in the Work. 4.6.2.2 Changes having a cost impact of less than ten thousand dollars ($10,000) shall not be processed as a Change Order unless such changes relate to written proposals and cost estimates requested by Owner as provided in Section 4.6.2.
Changes to the Contract Price. The value of any Work covered by a Change Order or of any request for an adjustment in the Contract Price will be determined as follows:
Changes to the Contract Price. (a) Except as set forth in Section 10.5.3(b), unless the Parties agree otherwise in writing, any Change Order required to be issued to increase the Contract Price as a result of an event described in Section 10.5.1 will increase the Contract Price by an amount equal to the Direct Costs incurred by Company solely in connection with such event. Notwithstanding the foregoing, if Owner submits a Change Order Request pursuant to Section 10.2.1, the Contract Price adjustment, if any, shall be limited to the amount determined in accordance with Section 10.2.1 and shall not include any additional amounts for Company’s Direct Costs. (b) In no event will Company be entitled to payment for any costs hereunder, including any Direct Costs, to the extent that such costs would have occurred, notwithstanding such event, due to the concurrent fault, actions or omissions of Company or its Subcontractors. (c) For purposes hereof, “Direct Costs” shall mean only the actual and reasonable out-of-pocket costs that are directly incurred by Company, and supported by documentation reasonably evidencing the amount and incurrence of such costs, as a result of the event giving rise to the Change Order for the following items: (i) compensation for Labor and Equipment utilized and in the direct employ of Company at the Project Site, at the rates as set forth in Company’s Rate Schedule; (ii) cost of materials and permanent equipment; (iii) payments properly made by Company to Subcontractors, service providers, consultants, and suppliers; (iv) rental charges of necessary machinery and equipment (but excluding hand tools) used at the Project Site; (v) Permit fees; and (vi) reasonable costs of mobilization and/or demobilization if the delay related to the event justifying the Change Order exceeds ten (10) continuous Days. Notwithstanding the foregoing, “Direct Costs” shall not include (A) salaries or other compensation (including costs of contributions, assessments, fringe benefits or taxes based on salaries or compensation) of Company’s Personnel at Company’s principal office and branch offices (except as provided in the previous sentence); (B) expenses of Company’s principal and branch offices; (C) Company’s profit, overhead or general expenses of any kind; (D) any replacement, repair or other costs or liabilities arising from any loss of or damage to any equipment, tools or other property owned or used by Company or its Subcontractors; (E) costs to correct or reperform any components of ...

Related to Changes to the Contract Price

  • CHANGES TO THE CONTRACT All contract modifications must be approved by the Dinwiddie County Administrator or his designee. The County will not assume responsibility for the cost of any changes made without proper consent. No fixed-price contract may be increased by more than twenty-five percent (25%) or $50,000, whichever is greater, without advance approval of the Dinwiddie County Board of Supervisors. Changes can be made to the contract in any of the following ways: A. The parties may agree in writing to modify the terms, conditions, or scope of the contract. Any additional goods or services to be provided shall be of a sort that is ancillary to the contract goods or services, or within the same broad product or service categories as were included in the contract award. Any increase or decrease in the price of the contract resulting from such modification shall be agreed to by the parties as a part of their written agreement to modify the scope of the contract. B. The County may order changes within the general scope of the contract at any time by written notice to the Contractor. Changes within the scope of the contract include, but are not limited to, things such as services to be performed, the method of packing or shipment, and the place of delivery or installation. The Contractor shall comply with the notice upon receipt, unless the Contractor intends to claim an adjustment to compensation, schedule, or other contractual impact that would be caused by complying with such notice, in which case the Contractor shall, in writing, promptly notify the County of the adjustment to be sought, and before proceeding to comply with the notice, shall await the County’s written decision affirming, modifying, or revoking the prior written notice. If the County decides to issue a notice that requires an adjustment to compensation, the Contractor shall be compensated for any additional costs incurred as the result of such order and shall give the County a credit for any savings. Said compensation shall be determined by one of the following methods: 1. By mutual agreement between the parties in writing; or 2. By agreeing upon a unit price or using a unit price set forth in the contract, if the work to be done can be expressed in units, and the Contractor accounts for the number of units of work performed, subject to the County’s right to audit the Contractor’s records and/or to determine the correct number of units independently; or 3. By ordering the Contractor to proceed with the work and keep a record of all costs incurred and savings realized. A markup for overhead and profit may be allowed if provided by the contract. The same markup shall be used for determining a decrease in price as the result of savings realized. The Contractor shall present the County with all vouchers and records of expenses incurred and savings realized. The County shall have the right to audit the records of the Contractor as it deems necessary to determine costs or savings. Any claim for an adjustment in price under this provision must be asserted by written notice to the County within thirty (30) days from the date of receipt of the written order from the County. Neither the existence of a claim nor a dispute resolution process, litigation or any other provision of this contract shall excuse the Contractor from promptly complying with the changes ordered by the County or with the performance of the contract generally.

  • THE CONTRACT PRICE A. This Contract is an indefinite-quantity contract for construction work and services. The Estimated Annual Value of this Contract is $2,000,000. This is only an estimate and may increase or decrease at the discretion of Sourcewell. B. The Contractor shall perform any or all Tasks in the Construction Task Catalog for the Unit Price appearing therein multiplied by the following Adjustment Factors:

  • C1 Contract Price In consideration of the Contractor’s performance of its obligations under the Contract, the Authority shall pay the Contract Price in accordance with clause C2 (Payment and VAT).

  • Contract Price The Contractor shall supply the Contractor Deliverables to the Authority at the Contract Price. The Contract Price shall be a Firm Price unless otherwise stated in Schedule 3 (Contract Data Sheet). Subject to clause G2 the Contract Price shall be inclusive of any UK custom and excise or other duty payable. The Contractor shall not make any claim for drawback of UK import duty on any part of the Contract Deliverables supplied which may be for shipment Overseas. D Intellectual Property

  • CHANGES TO THE CALCULATION OF INTEREST 10.1 Absence of quotations