Common use of Changes Clause in Contracts

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 140 contracts

Sources: Commercial Subcontract/Purchase Order, International Commercial Subcontract/Purchase Order, General Provisions for Subcontracts/Purchase Orders

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) description of services; (ii) drawings, designs, or specifications; (iiiii) method of shipping or packing; (iiiiv) place of inspection, acceptance, or point of delivery; (v) time of performance; and (ivvi) delivery scheduleplace of performance. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the this Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule time of performance will be subject to a price adjustment only. (c) SELLER must assert its right to an request any equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 49 contracts

Sources: General Provisions for Services, Time and Materials Subcontract, General Provisions for Subcontracts/Purchase Orders

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If the SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 18 contracts

Sources: General Provisions and Far Flowdown Provisions for Subcontracts/Purchase Orders for Commercial Items, Commercial Subcontract/Purchase Order, Commercial Subcontract/Purchase Order

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative Contracting Officer may at any time, by a written noticeorder, and without notice to sureties or assigneesthe sureties, make changes changes, within the general scope of this Contract contract, in any one anyone or more of the following: (i) drawingsDrawings, designs, or specificationsspecifications where the supplies to be furnished are to be specially manufactured for the Government in accordance therewith; (ii) method of shipping shipment or packing; and (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) . If any such change causes an increase or decrease in the cost of, or the time required for, the performance of any part of the work under this Contractcontract, LOCKHEED ▇▇▇▇▇▇ shall make whether changed or not changed by any such order, an equitable adjustment shall be made in the Contract contract price and/or or delivery schedule, or both, and modify this Contract the contract shall be modified in writing accordingly. Changes to Any claim by the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable contractor for adjustment under this clause must be asserted within thirty (30) 30 days from the date of receipt by the Contractor of the written change order from LOCKHEED ▇▇▇▇▇▇notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. If SELLER's proposed equitable adjustment includes Where the cost of property made obsolete or excess by as a result of a change is included in the changeContractor's claim for adjustment, LOCKHEED ▇▇▇▇▇▇ the Contracting Officer shall have the right to prescribe the manner of disposition of the such property. (d) . Failure to agree to any adjustment shall be resolved in accordance with a dispute concerning a question of fact within the "Disputes" meaning of the clause of this Contract. contract entitled "Disputes." However, nothing contained in this "Changes" clause shall excuse SELLER the Contractor from proceeding without delay in with the performance of this Contract contract as changed.

Appears in 14 contracts

Sources: Supply Contract, Supply Contract, Supply Contract

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) description of services; (ii) drawings, designs, or specifications; (iiiii) method of shipping or packing; (iiiiv) place of inspection, acceptance, or point of delivery; (v) time of performance; and (ivvi) delivery scheduleplace of performance. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the this Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule time of performance will be subject to a price adjustment only. (c) SELLER must assert its right to an request any equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If the SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 6 contracts

Sources: Time and Materials Subcontract, General Provisions and Far Flowdown Provisions for Subcontracts/Purchase Orders for Commercial Item Services, Commercial Subcontract/Purchase Order

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) description of services; (ii) drawings, designs, or specifications; ; (iiiii) method of shipping or packing; (iiiiv) place of inspection, acceptance, or point of delivery; (v) time of performance; and (ivvi) delivery scheduleplace of performance. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the this Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule time of performance will be subject to a price adjustment only. (c) SELLER must assert its right to an request any equitable adjustment under this clause within thirty three (303) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If the SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 2 contracts

Sources: Commercial Subcontract/Purchase Order, Time and Materials Commercial Subcontract

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: : (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: Subcontract Agreement

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Bomic Ltd Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ Bomic Ltd shall make an equitable adjustment in the Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. Bomic Ltd. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ Bomic Ltd shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: Subcontract/Purchase Order Agreement

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative Utilities may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, Statement of Work, or specificationsSpecifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, acceptance or point of delivery; and and/or (iv) delivery schedule. (b) If . Subject to Section 21, “Appropriation of Funds”, if any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make Utilities may agree to an equitable adjustment in the Contract price and/or delivery schedule, and modify this the Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to modified accordingly upon mutual written agreement by authorized representatives of the Parties. Any request by either Party for additional Goods or Services for changes in the manner or method of performance, shall be made only by written amendment, work change directive, or change order, which shall specify the part of the Contract affected by the change. Utilities shall not be liable for payment of any additional Goods or Services performed by Contractor not previously authorized by Utilities by written amendment, work change directive, or change order. Any claim for an equitable adjustment under this clause by Contractor must be submitted in writing to Utilities within thirty (30) days from the date of receipt notice of the written change order from LOCKHEED ▇▇▇▇▇▇. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have unless the right Parties agree in writing to prescribe the manner of disposition of the property. (d) a longer period. Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this ContractSection 20, “Dispute Resolution”. However, nothing contained in this "Changes" clause provision shall excuse SELLER Contractor from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: Goods and Services Contract

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by upon ninety (90) days’ written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: Commercial Subcontract/Purchase Order

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the Contract price and/or delivery schedule, schedule and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: General Provisions for International Subcontracts/Purchase Orders

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ shall make an equitable adjustment in the Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause paragraph within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇order. If the SELLER's proposed equitable adjustment ’s proposal includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: Letter Contract

Changes. (a) Only the Procurement Representative has authority to make changes to this Contract. All changes must be in writing and signed by the parties. (b) The LOCKHEED ▇▇▇▇▇▇ Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) drawings, designs, or specificationsdescription of services; (ii) method time of shipping or packingperformance; and (iiivi) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) performance. If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ ULA shall make an equitable adjustment in the this Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule time of performance will be subject to a price adjustment only. (c) SELLER . CONTRACTOR must assert its right to an request any equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇ULA. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER CONTRACTOR from proceeding without delay in the performance of this Contract as changed. (c) ULA personnel other than the Procurement Representative may from time to time render assistance or give technical advice or discuss or effect an exchange of information with CONTRACTOR’s personnel concerning the Work hereunder. No such action shall be deemed to be a change and shall not be the basis for equitable adjustment.

Appears in 1 contract

Sources: Commercial Purchase Orders/Agreements for Consultants

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ VETERANS TRADING COMPANY Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: (i) description of services; (ii) drawings, designs, or specifications; (iiiii) method of shipping or packing; (iiiiv) place of inspection, acceptance, or point of delivery; (v) time of performance; and (ivvi) delivery scheduleplace of performance. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ VETERANS TRADING COMPANY shall make an equitable adjustment in the this Contract price and/or delivery schedule, and modify this Contract accordingly. Changes to the delivery schedule time of performance will be subject to a price adjustment only. (c) SELLER must assert its right to an request any equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇VETERANS TRADING COMPANY. If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ VETERANS TRADING COMPANY shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: Contract

Changes. (a) The LOCKHEED ▇▇▇▇▇▇ AOSENSE Procurement Representative may at any time, by written notice, and without notice to sureties or assignees, make changes within the general scope of this Contract in any one or more of the following: : (i) drawings, designs, or specifications; (ii) method of shipping or packing; (iii) place of inspection, acceptance, or point of delivery; and (iv) delivery schedule. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of this Contract, LOCKHEED ▇▇▇▇▇▇ AOSENSE shall make an equitable adjustment in the Contract price and/or delivery schedule, schedule and modify this Contract accordingly. Changes to the delivery schedule will be subject to a price adjustment only. (c) SELLER must assert its right to an equitable adjustment under this clause within thirty (30) days from the date of receipt of the written change order from LOCKHEED ▇▇▇▇▇▇AOSENSE . If SELLER's proposed equitable adjustment includes the cost of property made obsolete or excess by the change, LOCKHEED ▇▇▇▇▇▇ AOSENSE shall have the right to prescribe the manner of disposition of the property. (d) Failure to agree to any adjustment shall be resolved in accordance with the "Disputes" clause of this Contract. However, nothing contained in this "Changes" clause shall excuse SELLER from proceeding without delay in the performance of this Contract as changed.

Appears in 1 contract

Sources: Subcontract/Purchase Order Agreement