Common use of Claim Submission Clause in Contracts

Claim Submission. Within 21 days of the Notice of Claim, the Contractor shall provide both KCDA and the Client in writing with a Claim, which shall include a clear description of the Claim, any and all changes in cost and in time to which the Contractor and its Subcontractors of any tier may be entitled under this Agreement for the Claim, and data supporting the Claim. The claim of a Subcontractor may be brought only through the Contractor and only after the Contractor notifies KCDA and the Client in writing that the Contractor has reviewed and agrees with the Claim. No act, omission, or knowledge, actual or constructive, of the Client shall in any way be deemed to be a waiver of the requirement for a timely written Claim unless the Client provides the Contractor with an explicit, unequivocal written waiver. Failure to comply with these requirements shall constitute waiver of the Claim.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract