Claims and Timely Assertion of Claims. The party filing a notice of demand for arbitration must assert in the demand all Claims then known to that party on which arbitration is permitted to be demanded.
Appears in 14 contracts
Sources: General Conditions of the Contract for Construction, Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Claims and Timely Assertion of Claims. The party filing a notice of demand for arbitration must assert in the demand all Claims claims then known to that party on which arbitration is permitted to be demanded.
Appears in 5 contracts
Sources: Mutual Confidentiality & Non Disclosure Agreement, Subcontract Agreement, Master Subcontract Agreement
Claims and Timely Assertion of Claims. The A party filing who files a notice of demand for arbitration must assert in the demand all Claims claims then known to that party on which arbitration is permitted to be demanded. When a party fails to include a Claim through oversight, inadvertence or excusable neglect, or when a claim has matured or been acquired subsequently, the arbitrator or arbitrators may permit amendment.
Appears in 4 contracts
Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect
Claims and Timely Assertion of Claims. The party filing a A Party who files notice of demand for arbitration must assert in the demand all Claims then known to that party Party on which arbitration is permitted to be demanded. When a Party fails to include a claim through oversight, inadvertence or excusable neglect, or when a claim has matured or been acquired subsequently, the Arbitrator may permit amendment.
Appears in 3 contracts
Sources: Master Agreement (Sprint Spectrum L P), Master Agreement (Sprint Spectrum Finance Corp), Master Agreement (Sprint Spectrum L P)
Claims and Timely Assertion of Claims. The party filing a notice Notice of demand Demand for arbitration Arbitration must assert in the demand Demand all Claims then known to that party on which arbitration is permitted to be demanded.
Appears in 3 contracts
Sources: General Conditions Agreement, General Conditions of the Agreement, General Conditions of the Agreement
Claims and Timely Assertion of Claims. The party Party filing a notice of demand for arbitration must assert in the demand all Claims claims then known to that party Party on which arbitration is permitted to be demanded.
Appears in 3 contracts
Sources: Construction Agreement, Construction Agreement, Construction Agreement
Claims and Timely Assertion of Claims. The A party filing who files a notice of demand for arbitration must assert in the demand all Claims claims then known to that party on which arbitration is permitted to be demanded. When a party fails to include a Claim through oversight, inadvertence or excusable neglect, or when a claim has matured or been acquired subsequently, the arbitrators may permit amendment.
Appears in 2 contracts
Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect
Claims and Timely Assertion of Claims. The party filing a notice of demand for arbitration must assert in the demand all Claims dispute(s) pertaining to the applicable Project then known to that party Party on which arbitration is permitted to be demanded.demanded.β
Appears in 1 contract
Sources: Architect's Service Order Agreement
Claims and Timely Assertion of Claims. The party filing a notice Notice of demand Demand for arbitration Arbitration must assert in the demand all Claims then known to that party on which arbitration is permitted to be demanded.
Appears in 1 contract