Common use of CLAIMS FOR ADDITIONAL COST Clause in Contracts

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.

Appears in 28 contracts

Sources: Contract for Construction, Contract for Construction, Contract for Construction

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes Design-Builder intends to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Workportion of the Work that relates to the Claim. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.

Appears in 26 contracts

Sources: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein in Section 15.1.3 shall be given before proceeding to execute the Workportion of the Work that is the subject of the Claim. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.

Appears in 15 contracts

Sources: Construction Manager/General Contractor Agreement, Guaranteed Maximum Price Amendment, Standard Form of Agreement Between Owner and Construction Manager as Constructor

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Article 13.

Appears in 11 contracts

Sources: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

CLAIMS FOR ADDITIONAL COST. If the Contractor Construction Manager wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4property.

Appears in 6 contracts

Sources: Agreement for Construction Management Services, Construction Management Services Agreement, Construction Management Services Agreement

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.6.

Appears in 5 contracts

Sources: Construction Manager at Risk Agreement, Construction Contract, Lease Agreement (Immunicon Corp)

CLAIMS FOR ADDITIONAL COST. If the Contractor Design-Builder wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4A.10.6.

Appears in 5 contracts

Sources: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Article XXI.

Appears in 4 contracts

Sources: Construction Contract, Construction Contract, Construction Contract

CLAIMS FOR ADDITIONAL COST. be given be endangeri If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before fore proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering ng life or property arising under Section 10.4Article 13.

Appears in 3 contracts

Sources: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

CLAIMS FOR ADDITIONAL COST. If the Contractor Construction Manager wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.5.

Appears in 2 contracts

Sources: Agreement Between Owner and Architect (Chukchansi Economic Development Authority), Construction Manager Agreement (Chukchansi Economic Development Authority)

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4when the giving of such notice would increase the risk of injury or damage to persons or property.

Appears in 2 contracts

Sources: Owner Contractor Agreement, Owner Contractor Agreement

CLAIMS FOR ADDITIONAL COST. If the Contractor Design Builder wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4property.

Appears in 2 contracts

Sources: Agreement for Design Build Services, Agreement for Continuing Design Build Services

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.6. Any change in the Contract Sum resulting from such Claim shall be authorized by written Modification.

Appears in 2 contracts

Sources: Services Agreement, Services Agreement

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.Paragraph 10.6. If the Contractor believes additional cost is involved for reasons including but not limited to: (1) a written interpretation from the Engineer; (2) an order by the Owner to stop the Work where the

Appears in 1 contract

Sources: Construction Agreement

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Workwork and such Claim shall be made and prosecuted in accordance with the terms of this Agreement. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 11.3.

Appears in 1 contract

Sources: Guaranteed Maximum Price Construction Agreement (Gaylord Entertainment Co /De)

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract SumSum under a Work Order, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4property.

Appears in 1 contract

Sources: Master Agreement for Civil Improvements

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.

Appears in 1 contract

Sources: Construction Contract (Symantec Corp)

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall notic be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency rela endangering life or property arising under Section 10.4.. pro elay

Appears in 1 contract

Sources: Construction Contract

CLAIMS FOR ADDITIONAL COST. If the ▇▇▇▇ Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.Paragraph 10.6. ▇▇▇▇ Contractor shall, upon recognition of a condition giving rise to a claim for additional cost, establish

Appears in 1 contract

Sources: Contract for Construction Manager at Risk

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as notic provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.Article 13. pro elay

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.property. If the Contractor believes additional cost is involved for reasons including but not limited to (1) a written interpretation from the ARCHITECT/ENGINEER, (2) an order by the Owner to stop the Work where the Contractor was not at fault,

Appears in 1 contract

Sources: Architectural/Engineering Services Agreement

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract SumGuaranteed Maximum Price, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.

Appears in 1 contract

Sources: Construction Contract (National Instruments Corp /De/)

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 18.4.

Appears in 1 contract

Sources: Construction Manager Agreement

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as is provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.

Appears in 1 contract

Sources: Construction Contract (Monarch Casino & Resort Inc)

CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.410.6.

Appears in 1 contract

Sources: Construction Contract (Sierra Pacific Resources /Nv/)

CLAIMS FOR ADDITIONAL COST. If if the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.

Appears in 1 contract

Sources: Construction Contract (Digex Inc/De)