Client’s information and obligations. The Client shall provide, or procure that other duty holders under the Building Safety Act provide, such information, documents, assistance and approvals as the Building Control Approver reasonably requires or requests from time to time in order to facilitate the timely provision of the Services and any Additional Work and to allow the Building Control Approver to comply with its obligations under the Building Safety Act. The Client shall be responsible for safe access to the Project being provided when the Building Control Approver reasonably requires it and shall procure such access and certification from any consultant, contractor or sub-contractor as is reasonably requested by the Building Control Approver. The Client shall give the Building Control Approver not less than 7 days’ written notice before any works forming part of the Project are commenced and shall keep the Building Control Approver regularly informed of the progress of the Project. The Client shall give advance written notice to the Building Control Approver at any stage at which an inspection by the Building Control Approver is required. The Client shall provide in a timely manner drawings and specifications including Site and block plans at not less than 1:1250 scale, showing all public services on or within 6 metres of the boundaries, and in sufficient detail to facilitate the proper serving of the Initial Notice and other legal documents as may be necessary. The Client shall ensure that the details completed in sections 1, 2 and 3 of the Initial Notice are correct before signing (and/or arranging for it to be signed) and returning it to the Building Control Approver for submission to the relevant local authority. The Client shall ensure the Initial Notice is returned to the Building Control Approver in sufficient time so that it can be submitted to the relevant local authority not less than 5 working days before works commence on Site. The Client shall be entirely responsible for the design, construction and management of the Project. The Client shall be entirely responsible for obtaining and implementing all necessary permits, licences, consents and approvals, unless the Parties have otherwise agreed in writing and provided always that the obtaining and implementing of any necessary permits, licences, consents and approvals by the Building Control Approver shall be deemed Additional Work for the purposes of this Contract. The Client and not the Building Control Approver shall be responsible for the Project’s compliance with the Building Regulations. The Services do not include and the Building Control Approver is not responsible for i) confirming whether the Building Regulations have been complied with, and/or ii) advising the Client and/or managing the Project to ensure that compliance with the Building Regulations is achieved. The Client shall notify the Building Control Approver immediately if it does not consider itself to be, or ceases to be, the person carrying out the works for the purposes of the Building Regulations and will confirm the identity of the person carrying out the works to the Building Control Approver. The Client will procure the necessary consents and approvals from any other person carrying out the works in a timely manner to enable the Building Control Approver to perform the Services and any Additional Work.
Appears in 2 contracts
Sources: Short Form Contract for the Appointment of a Building Control Approver, Short Form Contract for the Appointment of a Building Control Approver
Client’s information and obligations. 5.1. The Client shall provide, or procure that other duty holders under the Building Safety Act provide, such information, documents, assistance and approvals as the Building Control Approver reasonably requires or requests from time to time in order to facilitate the timely provision of the Services and any Additional Work and to allow the Building Control Approver to comply with its obligations under the Building Safety Act.
5.2. The Client shall be responsible for safe access to the Project being provided when the Building Control Approver reasonably requires it and shall procure such access and certification from any consultant, contractor or sub-contractor as is reasonably requested by the Building Control Approver.
5.3. The Client shall give the Building Control Approver not less than 7 days’ written notice before any works forming part of the Project are commenced and shall keep the Building Control Approver regularly informed of the progress of the Project.
5.4. The Client shall give advance written notice to the Building Control Approver at any stage at which an inspection by the Building Control Approver is required.
5.5. The Client shall provide in a timely manner drawings and specifications including Site and block plans at not less than 1:1250 scale, showing all public services on or within 6 metres of the boundaries, and in sufficient detail to facilitate the proper serving of the Initial Notice and other legal documents as may be necessary.
5.6. The Client shall ensure that the details completed in sections 1, 2 and 3 of the Initial Notice are correct before signing (and/or arranging for it to be signed) and returning it to the Building Control Approver for submission to the relevant local authority. The Client shall ensure the Initial Notice is returned to the Building Control Approver in sufficient time so that it can be submitted to the relevant local authority not less than 5 working days before works commence on Site.
5.7. The Client shall be entirely responsible for the design, construction and management of the Project. The Client shall be entirely responsible for obtaining and implementing all necessary permits, licences, consents and approvals, unless the Parties have otherwise agreed in writing and provided always that the obtaining and implementing of any necessary permits, licences, consents and approvals by will notify the Building Control Approver shall be deemed Additional Work for in writing of any Agent appointed to act on its behalf and of any change or dismissal of the purposes of this ContractAgent. The Client and not the Building Control Approver shall be responsible for the Project’s compliance with the Building Regulations. The Services do not include and the Building Control Approver is not responsible for i) confirming whether the Building Regulations have been complied with, and/or ii) advising Where the Client and/or managing appoints an Agent to act on its behalf, the Project Client confirms that the Agent is authorised to ensure that compliance with sign the Building Regulations is achievedInitial Notice (and or any other Notice) on its behalf wherever signed by the Agent.
5.8. The Client shall notify the Building Control Approver immediately if it does not consider itself to be, or ceases to be, the person carrying out the works for the purposes of the Building Regulations and will confirm the identity of the person carrying out the works to the Building Control Approver. The Client will procure the necessary consents and approvals from any other person carrying out the works in a timely manner to enable the Building Control Approver to perform the Services and any Additional Work.
Appears in 2 contracts
Sources: Contract for the Appointment of a Building Control Approver, Contract
Client’s information and obligations. 3.1. The Client shall provide, or procure that other duty holders under the Building Safety Act provide, such information, documents, assistance and approvals as the Building Control Approver reasonably requires or requests from time to time in order to facilitate the timely provision of the Services and any Additional Work and to allow the Building Control Approver to comply with its obligations under the Building Safety Act.
3.2. The Client shall be responsible for safe access to the Project being provided when the Building Control Approver reasonably requires it and shall procure such access and certification from any consultant, contractor or sub-contractor as is reasonably requested by the Building Control Approver.
3.3. The Client shall give the Building Control Approver not less than 7 days’ written notice before any works forming part of the Project are commenced and shall keep the Building Control Approver regularly informed of the progress of the Project. The Client shall give advance written notice to the Building Control Approver at any stage at which an inspection by the Building Control Approver is requiredare
3.4. The Client shall provide in a timely manner drawings and specifications including Site and block plans at not less than 1:1250 scale, showing all public services on or within 6 metres of the boundaries, and in sufficient detail to facilitate the proper serving of the Initial Notice and other legal documents as may be necessary.
3.5. The Client shall ensure that the details completed in sections 1, 2 and 3 of the Initial Notice are correct before signing (and/or arranging for it to be signed) and returning it to the Building Control Approver for submission to the relevant local authority. The Client shall ensure the Initial Notice is returned to the Building Control Approver in sufficient time so that it can be submitted to the relevant local authority not less than 5 working days before works commence on Site.
3.6. The Client shall be entirely responsible for the design, construction and management of the Project.
3.7. The Client shall be entirely responsible for obtaining and implementing all necessary permits, licences, consents and approvals, unless the Parties have otherwise agreed in writing and provided always that the obtaining and implementing of any necessary permits, licences, consents and approvals by the Building Control Approver shall be deemed Additional Work for the purposes of this Contract.
3.8. The Client and not the Building Control Approver shall be responsible for the Project’s compliance with the Building Regulations. The Services do not include and the Building Control Approver is not responsible for i) confirming whether the Building Regulations have been complied with, and/or ii) advising the Client and/or managing the Project to ensure that compliance with the Building Regulations is achieved.
3.9. The Client shall notify the Building Control Approver immediately if it does not consider itself to be, or ceases to be, the person carrying out the works for the purposes of the Building Regulations and will confirm the identity of the person carrying out the works to the Building Control Approver. The Client will procure the necessary consents and approvals from any other person carrying out the works in a timely manner to enable the Building Control Approver to perform the Services and any Additional Work.
Appears in 1 contract