CLIENT’S OBLIGATIONS AND WARRANTIES. 11.1 The Client shall provide suitable access to enable the Contractor to undertake the Works. 11.2 The client will supply all necessary water and electricity for the carrying out of the agreed work without charge to the Contractor. 11.3 Unless otherwise agreed, any necessary local authority approvals will be sought and gained by the Client prior to commencement of the agreed work. Copies of all relevant permissions and approvals are also to be forwarded to the Contractor prior to commencement of the agreed work. Any fees for such approval will be paid by the Client to the Trade Partner. 11.4 Unless otherwise agreed the Client assumes full responsibility for following any pertinent procedures required under The Party Wall etc. Act 1996. 11.5 It is the Client’s responsibility to comply with any pertinent rules under the most recent Construction (Design and Management) Regulation. 11.6 Unless otherwise agreed it is the Client’s sole responsibility to ensure that it has obtained the relevant permissions for the Contractor to undertake the Works, including but not limited to permission from any landlord, neighbour and utility company. 11.7 Unless otherwise agreed it is the Client’s sole responsibility to obtain and produce a relevant asbestos report. 11.8 The Contractor will not accept any liability for any direct or consequential loss as a result of the Client’s failure to comply with any of the requirements at Clause 12. 11.9 In the event of a breach of any of the requirements at Clause 12 the Contractor may elect, at its sole discretion, to halt Works until such time as the relevant requirements are met, and charge abortive costs as appropriate. The Contractor may also elect to terminate the agreement as per clause 18.
Appears in 1 contract
Sources: Client Terms and Conditions
CLIENT’S OBLIGATIONS AND WARRANTIES. 11.1 12.1 The Client client shall provide suitable access to enable the Contractor to undertake the Works.
11.2 12.2 The client will supply all necessary water and electricity for the carrying out of the agreed work without charge to the Contractor.
11.3 12.3 Unless otherwise agreed, any necessary local authority approvals will be sought and gained by the Client prior to commencement of the agreed work. Copies of all relevant permissions and approvals are also to be forwarded to the Contractor prior to commencement of the agreed work. Any fees for such approval will be paid by the Client to the Trade PartnerClient.
11.4 12.4 Unless otherwise agreed the Client assumes full responsibility for following any pertinent procedures required under The Party Wall etc. Act 1996.
11.5 It 12.5 Unless otherwise agreed it is the Client’s responsibility to comply with any pertinent rules under the most recent Construction (Design and Management) Regulation.
11.6 12.6 Unless otherwise agreed it is the Client’s sole responsibility to ensure that it has obtained the relevant permissions for the Contractor to undertake the Works, including but not limited to permission from any landlord, neighbour and utility company.
11.7 12.7 Unless otherwise agreed it is the Client’s sole responsibility to obtain and produce a relevant asbestos report.
11.8 12.8 The Contractor will not accept any liability for any direct or consequential loss as a result of the Client’s failure to comply with any of the requirements at Clause 12.
11.9 12.9 In the event of a breach of any of the requirements at Clause 12 the Contractor may elect, at its sole discretion, to halt Works until such time as the relevant requirements are met, and charge abortive costs as appropriate. The Contractor may also elect to terminate the agreement as per clause 18.
Appears in 1 contract
Sources: Terms and Conditions