COMBINATION RATE. 1.) On all heavy industrial and heavy building work, such as factories; oil refineries; power plants; chemical plants; water, oil, gas and chemical tanks, flood control projects and levees; coal gasification plants; etc., the following shall apply: (a) An engineer is permitted to operate two to four pumps, or a small mixer and a pump or two to four welding machines, or two air compressors when under 200 cu. Ft. capacity, or two large air compressors of over 200 cu. Ft. capacity, when hooked in manifold, or one to five mechanical heaters. (b) An operator shall be permitted to operate one throttle valve at the combination rate. (c) Combination rate shall mean premium pay of one dollar ($1.00) per hour above the basic hourly rate of pay. It is understood and agreed as follows: When one air compressor under 200 cu. ft. capacity, or one pump, or one welding machine or one conveyor or self-propelled concrete saw is to be put into operation for a period of no longer than a total of four hours in any one work shift and an oiler is employed on the job, the oiler (apprentice engineer) may operate the one machine for the period (four hours or less) at the combination rate. When there is no oiler (apprentice engineer) on the job, an engineer shall be employed to operate any of the mentioned machines of this Article regardless of the amount of time the machine is to be operated. Where more than one of the mentioned machines of this Article are operated, an engineer shall be employed to operate the machines at the combination rate. The oiler (apprentice engineer) is not permitted to operate when more than one machine is in operation. 2.) On all other types of work an oiler will be employed at the Group 2 rate to operate one (1) to four (4) pumps, or a small mixer and a pump, or one (1) to four (4) welding machines, or two (2) air compressors when under 200 cu. ft. capacity, or two (2) large air compressors of over 200 cu. ft. capacity when hooked in manifold, or one (1) to five (5) mechanical heaters, or one (1) conveyor, or one self-propelled concrete saw in addition to his duties as a crane oiler.
Appears in 2 contracts
Sources: Construction Contract, Construction Agreement
COMBINATION RATE. β
1.) On all heavy industrial and heavy building work, such as factories; oil refineries; power plants; chemical plants; water, oil, gas and chemical tanks, flood control projects and levees; coal gasification plants; etc., the following shall apply:
(a) a. An engineer is permitted to operate two to four pumps, or a small mixer and a pump pump, or two to four welding machines, or two air compressors when under 200 cu. Ftft. per min. capacity, or two large air compressors of over 200 cu. Ftft. per min. capacity, when hooked in manifold, or one to five mechanical heaters.
(b) b. An operator shall be permitted to operate one throttle valve at the combination rate.
(c) c. Combination rate shall mean premium pay of one dollar ($1.00) per hour above the basic hourly rate of pay. It is understood and agreed as follows: When one air compressor under 200 cu. ft. per min. capacity, or one pump, or one welding machine or one conveyor or self-propelled concrete saw is to be put into operation for a period of no longer than a total of four hours in any one work shift and an oiler is employed on the job, the oiler (apprentice engineer) may operate the one machine for the period (four hours or less) at the combination rate. When there is no oiler (apprentice engineer) on the job, an engineer shall be employed to operate any of the mentioned machines of this Article regardless of the amount of time the machine is to be operated. Where more than one of the mentioned machines of this Article are operated, an engineer shall be employed to operate the machines at the combination rate. The oiler (apprentice engineer) is not permitted to operate when more than one machine is in operation.
2.) On all other types of work work, an oiler will be employed at the Group 2 rate to operate one
one (1) to four (4) pumps, or a small mixer and a pump, or one (1) to four (4) welding machines, or two (2) air compressors when under 200 cu. ft. per min. capacity, or two (2) large air compressors of over 200 cu. ft. per min. capacity when hooked in manifold, or one (1) to five (5) mechanical heaters, or one (1) conveyor, or one self-propelled concrete saw in addition to his duties as a crane oiler.
Appears in 1 contract