Commencement of the Works. Before the commencement of the WUC, the Contractor shall: provide the Principal with a copy of the Contractor’s construction programme referred to in clause 43; effect all insurances required under clauses 7. and 8. and lodge evidence of such with the Superintendent; give the Superintendent seven (7) days’ notice in writing of the proposed date of commencement of the Works; obtain approval from the Superintendent for the nominated Contractor’s Representative; and provide to the principal a geotechnical report specifying the Site’s engineering classification.
Commencement of the Works. The Organisation must Commence the Works on or before [insert].
Commencement of the Works. 38.1 The Contractor shall not commence the Works prior to the issuance of the Commencement Order (“Commencement Order”).
38.2 Within sixty (60) days following the Signature Date, the Contractor shall be responsible to fulfill all the necessary conditions to obtain the Commencement Order. Any failure thereof, shall entitle NI to receive from the Contractor Liquidated Damages for delay, as detailed in Appendix B (Contractual Milestones).
38.3 The achievement of the Commencement Order shall be subject to the fulfillment of the following conditions:
Commencement of the Works. At least seven days before commencement of the works, the Developer shall notify the Section Engineer: Contract Management of Council of the commencement date. Such Notice shall be accompanied by all relevant documentation, such as but not limited to:
a) A copy of the signed Development Agreement;
b) 1 copy of the set of approved construction drawings (released for construction);
c) 1 copy of the construction contract document containing the specifications.
Commencement of the Works. The works associated with the Environmental Monitoring System and component parts is subject to the complete performance of the following condition precedent, the receipt by FMSL of a written notice from the Purchaser that the works may be commenced as detailed in the Start on Site form. The provision of clear, well lit, safe, and uninterrupted access during the whole of the works.
Commencement of the Works. The Organisation must commence the Infrastructure Works within [insert] months after the Date of this Agreement. The Organisation must commence the Residential Works by [insert].
Commencement of the Works.
2.1 prior notice of such commencement has been given by the ALT to the Owner’s Representative;
Commencement of the Works. (a) The Organisation must obtain the Commonwealth's approval to commence that part of the Works that relates to the construction and/or fit-out of the Works. The Commonwealth may give or withhold its approval at its discretion but will only provide such approval:
(i) after the Organisation has delivered, to the Commonwealth's satisfaction, the relevant Deliverables set out in the Deliverables and Milestones Schedule;
(ii) if it is satisfied that the Organisation has complied with the requirements set out in clause 23.10(b).
(b) Without limiting clause 23.10(a) or the Organisation's obligations under clause 23.10, the Organisation must not commence that part of the Works that relates to the construction and/or fit-out of the Works until it has:
(i) obtained written approval from the Commonwealth under clause 23.10(a) (which will not be unreasonably withheld);
(ii) obtained all relevant Approvals required under clause 3.1 that are necessary to enable the Commencement of the Works;
(iii) obtained all insurances required under clause 16.1(a);
(iv) complied with its obligations under clause 4.3(a); and
(v) provided security to the Commonwealth in accordance with clause 5.1.
(c) The Organisation must:
(i) obtain written approval from the Commonwealth under clause 23.10(a); and
(ii) commence that part of the Works that relates to the construction and/or fit-out of the Works, on or before the date specified for the Commencement of the Works in Item 5 of Schedule 1.
Commencement of the Works. The Works shall commence within 7 days of the date of the Licence commencing the Construction Works Construction Works: The construction works to be carried out by the Licensee on the Licensee’s Land edged red on the attached Plan in accordance with the Planning Permission dated 17th January 2022 with reference under number EPF/1080/19. Licence Period: the period from and including the date hereof until the date on which this Licence is determined in accordance with Clause 4 or the Permitted Period expires. Parking and Storage Area: They are shown edged blue on the Plan attached hereto.
Commencement of the Works. 15.1 Instruction by the ALT