Commissioning and Start Up Clause Samples

The 'Commissioning and Start Up' clause defines the procedures and responsibilities for testing, activating, and verifying the proper functioning of a facility, system, or equipment before it is officially put into operation. Typically, this clause outlines the steps required for initial inspections, performance testing, and the handover process from the contractor to the owner, ensuring all systems meet agreed-upon specifications. Its core function is to ensure that the delivered project is fully operational, safe, and compliant with contractual requirements before final acceptance, thereby reducing the risk of defects or operational failures after handover.
Commissioning and Start Up. With the Owner’s maintenance personnel and the Consultants, direct the check- out of utilities, operations systems and equipment for readiness and assist in their initial commissioning, start-up and testing by the General Contractor.
Commissioning and Start Up. Mechanical Completion of the Facility; first fire of each Unit; and start-up and tuning of each Unit;
Commissioning and Start Up. Promptly after Mechanical Completion has occurred, THE BUYER shall commence commissioning and start-up of the Plant in order to bring the Plant into a stable operating condition ready for performance testing. THE BUYER shall notify THE SELLER in writing 10 (ten) working days in advance of the number of personnel to be assigned for and the envisaged duration of the requested Advisory Services. Upon such written request, THE SELLER shall assign qualified personnel for and render Advisory Services during the commissioning, start-up and/or the subsequent performance testing of the Plant, as the case may be. Advisory Services shall not exceed $200,000.00, for commissioning, startup and performance testing of the plant, in Article 5.2, unless delays extend the period of Advisory Services due to errors by persons other than THE SELLER. The foregoing limitation excludes any Advisory Services that may be requested by BUYER of SELLER not in conjunction with commissioning, startup and performance testing related activities.
Commissioning and Start Up. After the ▇▇▇▇▇ Complex is Mechanically Complete, Owner shall, with the oversight and cooperation of the Contractor and the Independent Engineer, commence Commissioning and Start-up of the ▇▇▇▇▇ Complex. Contractor shall be responsible for monitoring Commissioning and Start-up in order to determine whether such activities are conducted in accordance with this Contract, the Start-up Protocol, the Standards, good operating practices and in conformance with the requirements of the Turnkey Specifications and shall provide immediate oral notice to Owner's Representative and the Independent Engineer, confirmed in writing within five (5) days, if any part of Commissioning or Start-up is not conducted in accordance with such requirements. Contractor shall not have any defense to its liabilities hereunder based on improper procedures or any other occurrences or conditions whatsoever during Commissioning unless notice is timely given as required in the preceding sentence. In addition, Contractor shall have the right to request that Owner, and Owner agrees to, stop any Commissioning or Start-up activities that Contractor reasonably believes will adversely affect the operation of the ▇▇▇▇▇ Complex or achievement of the Guaranteed Values. Owner's failure to comply with such requests or to follow the Start-up Protocol shall entitle Contractor to a claim of Owner-Caused Delay, provided, however, that any delay failure to abide by the Start-up Protocol by -------- ------- the Contractor shall not entitle the Contractor to any claims for Owner-Caused Delay.
Commissioning and Start Up. (Budget Period 2) - This task includes component testing and the commissioning of all components of the project, from core processes to buildings and utilities. This task also includes sequential start-up of the facility and operation to a steady- state.
Commissioning and Start Up 

Related to Commissioning and Start Up

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Synchronization, Commissioning and Commercial Operation 5.1.1 The SPG shall give PGVCL at least thirty (30) days’ advanced preliminary written notice and at least fifteen (15) days’ advanced final written notice, of the date on which it intends to synchronize the Solar Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPG to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPG at its generation facility of the Power Project at its own cost. The SPG shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/ and checking/verification is made by the concerned authorities of the PGVCL. 5.1.4 The SPG shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the SPG will inject in-firm power to grid from time to time to carry out operational/ functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization / Connectivity of the Project with the grid shall not to be considered as Commissioning of the Project. 5.1.5 The SPG shall commission the Project within nine (9) Months from the Date of execution of this PPA. Declaration of COD shall be certified by the commissioning committee. 5.1.6 The Parties agree that for the purpose of commencement of the supply of electricity by SPG to PGVCL, liquidated damages for delay etc., the Scheduled Commissioning Date as defined in this Agreement shall be the relevant date.

  • Construction Phase Services 3.1.1 – Basic Construction Services

  • Start-Up and Synchronization Consistent with the mutually acceptable procedures of the Developer and Connecting Transmission Owner, the Developer is responsible for the proper synchronization of the Large Generating Facility to the New York State Transmission System in accordance with NYISO and Connecting Transmission Owner procedures and requirements.

  • Training and Support Licensor shall offer installation support to the Licensee and each of the Members, including assisting with the implementation of any Licensor software. Licensor will provide appropriate training to Licensee and Member staff relating to the use of the Licensed Materials and any Licensor software. Licensor will offer reasonable levels of continuing support to assist Licensee and Members in use of the Licensed Materials, including providing help files and other appropriate user documentation in connection with the use of and access to Licensed Materials. Licensor will, at a minimum, make its personnel available by email, telephone or via the Web, or in person during Licensor’s regular business hours, Monday through Friday, for training and user access support.