Commissioning Procedure. i) At the time of commissioning, the Commissioning Committee shall verify compliance of technical parameter of the Project as per Annexure A of the RfS document. ii) SPDs shall give to the Buying Entity / REMC Ltd. at least 60 (Sixty) Days advance preliminary written notice and at least 30 (Thirty) Days advance final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. The SPD shall be solely responsible for any delay or non- receipt of the notice by the concerned agencies, which may in-turn affect the Commissioning Schedule of the Project. iii) A Solar PV Project will be considered as commissioned if all equipment as per rated project capacity has been installed and energy has flown into thegrid. iv) SPD shall ensure that the equipment up to the rated Capacity has been installed and completed in all respects before the Schedule Commissioning Date. The same shall be verified by the Committee during their visit to the Project and documented as per prescribedformat.