Compensable Items. The liability of the Department for claims will be limited to the following specifically identified items of cost, insofar as they have not otherwise been paid for by the Department, and insofar as they were caused solely by the actions or omissions of the Department or its agents (except that with regard to payment for extra work, the Department will pay to the CMR the Overhead and profit percentages provided for in Article 13, Compensation for Changes in the Work): .1 Additional Project-site labor expenses. .2 Additional costs for materials. .3 Additional, unabsorbed Project-site Overhead (e.g., for mobilization and demobilization). .4 Additional costs for active equipment.
Appears in 2 contracts
Sources: Standard Form of Agreement Between Owner and Construction Manager at Risk (Cmr) for Guaranteed Maximum Price (Gmp), Standard Form of Agreement Between Owner and Construction Manager at Risk (Cmr) for Guaranteed Maximum Price (Gmp)
Compensable Items. The liability of the Department for claims will be limited to the following specifically identified items of cost, insofar as they have not otherwise been paid for by the Department, and insofar as they were caused solely by the actions or omissions of the Department or its agents (except that with regard to payment for extra work, the Department will pay to the CMR the Overhead and profit percentages provided for in Article 13, Compensation for Changes in the Work): .1 Additional Project-site labor expenses. .2 Additional costs for materials. .3 Additional, unabsorbed Project-site Overhead (e.g., for mobilization and demobilization). .4 Additional costs for active equipment.
Appears in 1 contract
Sources: Guaranteed Maximum Price Amendment
Compensable Items. The liability of the Department for claims will be limited to the following specifically identified items of cost, insofar as they have not otherwise been paid for by the Department, and insofar as they were caused solely by the actions or omissions of the Department or its agents (except that with regard to payment for extra work, the Department will pay to the CMR Contractor the Overhead and profit percentages provided for in Article 13, Compensation for Changes in the Work): .1 13.):Additional Project-site labor expenses.
38.4.1.1 Additional Project-site labor expenses. .2 .
38.4.1.2 Additional costs for materials. .3 .
38.4.1.3 Additional, unabsorbed Project-site Overhead (e.g., for mobilization and demobilization). .4 .
38.4.1.4 Additional costs for active equipment.
38.4.1.5 For each Day of Project delay or suspension caused solely by actions or omissions of the Department either:
Appears in 1 contract
Sources: Subcontract Agreement