Completion and Final Payment. When Contractor certifies that the Work is finally complete, Contractor shall submit to the County a list of items completed or corrected. When the County determines that the Work is finally complete, a Certificate of Final Completion will be prepared establishing the date of Final Completion. If the Work is complete in full accordance with this Contract and this Contract has been fully performed, County may proceed with payment. Any guarantees or warranties, express or implied, required by the Contract or arising under law shall commence on the date of Final Completion of the Work. The Certificate of Final Completion shall be submitted to County and Contractor for their written acceptance of the responsibilities assigned to them in such certificate.