Common use of COMPLETION AND RENTAL COMMENCEMENT DATE Clause in Contracts

COMPLETION AND RENTAL COMMENCEMENT DATE. When Landlord's Architect has furnished Landlord with a certificate that the work to be done by Landlord pursuant hereto has been substantially complete, Completion of the Premises shall be deemed to have occurred and possession thereof deemed delivered to Tenant for all purposes of the Lease including, without limitation, Paragraph 3 thereof. Landlord and Tenant understand that pursuant to Paragraph 3 of the Lease, Tenant's obligation to pay Rent thereunder shall not commence until Landlord's Architect has furnished such certificate; provided, however, that if Landlord shall be delayed in substantially completing said work as a result of:

Appears in 2 contracts

Sources: Assembly/Light Manufacturing/Office Lease (Triton Network Systems Inc), Assembly/Light Manufacturing/Office Lease (Triton Network Systems Inc)