Completion of Punch List items. 6.26.3.1 Within 30 days after the date of Substantial Completion and before the date of Contract Completion, the DB shall complete all items on the Contracting Authority’s Punch List. After completing all items on the Contracting Authority’s Punch List, the DB shall provide a written request for Final Inspection of the Work to the Contracting Authority. .1 If Work on the Contracting Authority’s Punch List cannot be timely completed, the DB shall justify in writing to the reasonable satisfaction of the Contracting Authority the reasons the items cannot be completed, and the DB may propose, for the Contracting Authority’s approval, a time when the DB shall complete those items. .2 Within 3 business days after receipt of the DB’s request for Final Inspection, the Contracting Authority shall complete a Final Inspection of the Work for compliance with the Contract Documents. .3 If multiple inspections of items on the Contracting Authority’s Punch List are required due to the DB’s failure to properly and timely complete them, the DB shall pay any additional costs incurred by the Contracting Authority and Owner resulting from any attendant delay and re-inspections. The Contracting Authority may deduct those additional costs from payments then or thereafter due the DB. If payments then or thereafter due the DB are not sufficient to cover those amounts, the DB shall immediately pay the amount of the insufficiency to the Owner. 6.26.3.2 If the Project is administered using the State’s web-based project management software, the DB shall receive the Contracting Authority’s Punch List and submit its request for Final Inspection, using the “Punch List” business process.
Appears in 2 contracts
Sources: Professional Services, Professional Services