Common use of Completion of Punch List items Clause in Contracts

Completion of Punch List items. Contractor shall proceed promptly to complete and correct the Punch List Items no later than thirty (30) Days after the Substantial Completion Date. On a weekly basis after the Substantial Completion Date, Contractor shall update the Punch List to include the date(s) that items listed on such Punch List are completed by Contractor and accepted by Owner. Notwithstanding the foregoing, the items listed on such Punch List shall not be considered complete until Owner shall have inspected such Punch List Items and acknowledged, by notation on the updated Punch List, that such item of Work is complete.

Appears in 2 contracts

Sources: Build Transfer Agreement, Engineering, Procurement and Construction Agreement