Common use of Completion Reports Clause in Contracts

Completion Reports. 73.1 On completion of each project, or at the end of key stages within a project if COI so requests, the Contract will provide a summary of the work carried out to include his assessment of successes/failures and potential improvements that could be made.

Appears in 1 contract

Sources: Services Framework Agreement

Completion Reports. 73.1 84.1 On completion of each project, or at the end of key stages within a project if COI so requests, the Contract Contractor will provide a summary of the work carried out to include his assessment of successes/failures and potential improvements that could be made.

Appears in 1 contract

Sources: Framework Agreement